Home / Browse projects / Surat, Gujarat / BARBELLA PHASE-1

Valid until 30 Jun 2025 Residential/Group Housing project

BARBELLA PHASE-1

By NIRANT HOMES

RG-GJ-44831 · RERA PR/GJ/SURAT/OLPAD/Others/RAA00098/070917 · Last updated on GujRERA portal: 28 Jun 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2025Possession promisedno revision filed
9 of 81Construction stages doneacross 9 buildings; furthest along: Excavation, 60%
82 of 177Units unsoldnot recorded sold or booked
Jump to the 46 documents Report an error

BARBELLA PHASE-1 is a Residential/Group Housing project by NIRANT HOMES in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/OLPAD/Others/RAA00098/070917 on 7 Sep 2017. Possession is promised by 30 Jun 2025. 95 of the 177 units on this registration are recorded sold or booked, and 9 of 81 construction stages are filed complete.

At a glance

Project

  • NameBARBELLA PHASE-1
  • TypeResidential/Group Housing
  • Location
    • BLOCK NO 1350- BARBODHAN VILLEGE
    • BHESAN BARBODHAN ROAD
    • BARBODHAN
    • OLPAD
    • Barbodhan
    • Olpad
    • Surat
    • 395005
  • Pincode395005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/OLPAD/Others/RAA00098/070917
  • ReraGenie IDRG-GJ-44831

Builder

  • NameNIRANT HOMES
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2017PromisedJun 2025

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2025
  • Registered on7 Sep 2017
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings9 building records
  • Documents filed46 files

Current status

54%95 of 177 units booked
43.3%Of the estimated cost spent so far

Figures as on 28 Jun 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
H---707
I---101
A---17017
B---37037
C---12012
D---72072
E---606
F---15015
G---10010

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 28 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Excavation, at 60%.

H22%
ActivityProgress
Excavation33%
Podiums (if any)Not applicable
Plinth33%
Stilt Floor33%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats33%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing33%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%
I100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A23%
ActivityProgress
Excavation29%
Podiums (if any)Not applicable
Plinth29%
Stilt Floor29%
Slabs of Super Structure29%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats29%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing29%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing29%
B53%
ActivityProgress
Excavation53%
Podiums (if any)Not applicable
Plinth53%
Stilt Floor53%
Slabs of Super Structure53%
Internal walls, internal plaster, floorings, doors and windows within flats53%
Sanitary fittings within the flats53%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks53%
External plumbing and external plaster, elevation, completion of terraces with waterproofing53%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing53%
C13%
ActivityProgress
Excavation20%
Podiums (if any)Not applicable
Plinth20%
Stilt Floor20%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%
D59%
ActivityProgress
Excavation60%
Podiums (if any)Not applicable
Plinth60%
Stilt Floor60%
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats55%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
E0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F30%
ActivityProgress
Excavation30%
Podiums (if any)Not applicable
Plinth30%
Stilt Floor30%
Slabs of Super Structure30%
Internal walls, internal plaster, floorings, doors and windows within flats30%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing30%
G53%
ActivityProgress
Excavation55%
Podiums (if any)Not applicable
Plinth55%
Stilt Floor55%
Slabs of Super Structure55%
Internal walls, internal plaster, floorings, doors and windows within flats55%
Sanitary fittings within the flats55%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 28 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area77,600 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 68.63 cr
Cost incurredRs 29.71 cr
Spent of the estimate43.29%
BuildingWingEstimatedIncurred
ANARs 7.63 crRs 3.30 cr
BNARs 7.63 crRs 3.30 cr
CNARs 7.63 crRs 3.30 cr
DNARs 7.63 crRs 3.30 cr
ENARs 7.63 crRs 3.30 cr
FNARs 7.63 crRs 3.30 cr
GNARs 7.63 crRs 3.30 cr
HNARs 7.63 crRs 3.30 cr
INARs 7.63 crRs 3.30 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJITKUMAR B JARIWALA
EngineerJALILBHAI ABDULBHAI SHEIKH

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/OLPAD/Others/RAA00098/070917 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 Jun 2025
Accountant's certificate (Form 3)28 Jun 2025
Site photograph, H26 Jun 2025
Site photograph, I26 Jun 2025
Site photograph, A26 Jun 2025
Site photograph, B26 Jun 2025
Site photograph, C26 Jun 2025
Site photograph, D26 Jun 2025
Site photograph, E26 Jun 2025
Site photograph, F26 Jun 2025
Site photograph, G26 Jun 2025
Engineer's certificate (Form 2)6 Oct 2024
Engineer's certificate annexure6 Oct 2024
RERA registration certificate7 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

54%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep BARBELLA PHASE-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Barbodhan2,600+ in Surat

Builder: NIRANT HOMES

NIRANT HOMES has 1 registration on GujRERA, including BARBELLA PHASE-1. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if BARBELLA PHASE-1 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of BARBELLA PHASE-1?

The registered promoter entity is NIRANT HOMES, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in BARBELLA PHASE-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BARBELLA PHASE-1?

The professionals named in the filing: Architect: AJITKUMAR B JARIWALA; Engineer: JALILBHAI ABDULBHAI SHEIKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BARBELLA PHASE-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BARBELLA PHASE-1. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BARBELLA PHASE-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.