Home / Browse projects / Rajkot, Gujarat / Balaji Upvan

Valid until 30 Apr 2027 Mixed Development project

Balaji Upvan

By SHANTI CONSTRUCTION

RG-GJ-94312 · RERA PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14927/100325/311226 · Last updated on GujRERA portal: 3 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
14 of 20Construction stages doneacross 2 buildings; furthest along: Sanitary fittings within the flats, 75%
64 of 148Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

Balaji Upvan is a Mixed Development project by SHANTI CONSTRUCTION in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14927/100325/311226 on 10 Mar 2025. Possession is promised by 30 Apr 2027. 84 of the 148 units on this registration are recorded sold or booked, and 14 of 20 construction stages are filed complete.

At a glance

Project

  • NameBalaji Upvan
  • TypeMixed Development
  • Location
    • Balaji Upvan
    • Mavdi Revenue Survey No 343 Paiki 1
    • Plot No 118 to 139
    • Near Vagad Chowk
    • 80 Feet Road
    • Mavdi
    • Mavdi
    • Rajkot
    • 360004
  • Pincode360004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14927/100325/311226
  • ReraGenie IDRG-GJ-94312

Builder

  • NameSHANTI CONSTRUCTION
  • Entity typePARTNERSHIP FIRM
  • Other registrations4 more →

Key dates

this monthRegisteredMar 2025PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on10 Mar 2025
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed37 files

Current status

57%84 of 148 units booked
56.6%Of the estimated cost spent so far

Figures as on 3 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block B---48048
Block A---4456100

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 3 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 20 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary fittings within the flats, at 75%.

Block B92%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
Block A92%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats75%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%

Progress on shared amenities19

As on 3 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes75%
Storm water drainsYes75%
Landscaping and tree plantingYes75%
Street lightingYes75%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes75%
Water conservation, rain water harvestingYes75%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Fire fightingYes75%
Drinking water facilitiesYes75%
Emergency evacuationYes75%
Use of renewable energyYes75%
SecurityYes75%
Letter boxYes75%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,899 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.10 cr
Cost incurredRs 5.15 cr
Spent of the estimate56.63%
BuildingWingEstimatedIncurred
Block ANARs 5.75 crRs 3.26 cr
Block BNARs 3.35 crRs 1.90 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAITRI UPENDRA MODI
EngineerASHWINKUMAR MANILAL LODHIYA

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/MAA14927/100325/311226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)3 Apr 2026
Engineer's certificate (Form 2)1 Apr 2026
Engineer's certificate annexure1 Apr 2026
Architect's certificate (Form 1)30 Mar 2026
Site photograph, Block B30 Mar 2026
Site photograph, Block A30 Mar 2026
RERA registration certificate10 Mar 2025
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

57%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep Balaji Upvan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mavdi1,800+ in Rajkot

2 kmBalaji UpvanOther 375Dot size: filed unitsN

Filed coordinates, straight-line distance. 375 registered projects within 2 km.

Builder: SHANTI CONSTRUCTION

SHANTI CONSTRUCTION has 5 registrations on GujRERA, including SHANTI RESIDENCY and SHANTIKUNJ BLISS. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if Balaji Upvan is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Balaji Upvan?

The registered promoter entity is SHANTI CONSTRUCTION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Balaji Upvan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Balaji Upvan?

The professionals named in the filing: Architect: MAITRI UPENDRA MODI; Engineer: ASHWINKUMAR MANILAL LODHIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Balaji Upvan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Balaji Upvan. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Balaji Upvan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.