Home / Browse projects / Ahmedabad, Gujarat / ASHRAYA - 9

Valid until 31 Aug 2020 Mixed Development project

ASHRAYA - 9

By KEVAL VISION CORPORATION

RG-GJ-78599 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01194/EX1/290720 · Last updated on GujRERA portal: 5 Mar 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2020Possession promisedmoved 26 months from the original
108 of 108Construction stages doneacross 12 buildings; every applicable stage filed complete
3 of 386Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

ASHRAYA - 9 is a Mixed Development project by KEVAL VISION CORPORATION in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01194/EX1/290720 on 3 Jan 2018. Possession is promised by 31 Aug 2020. The completion date has moved by 26 months from the original filing. 383 of the 386 units on this registration are recorded sold or booked, and 108 of 108 construction stages are filed complete.

At a glance

Project

  • NameASHRAYA - 9
  • TypeMixed Development
  • Location
    • ASHRAYA 9
    • G S T COMPOUND
    • NR KHODIYAR TEMPLE
    • NEW RANIP
    • Kali
    • Daskroi
    • Ahmedabad
    • 382470
  • Pincode382470
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01194/EX1/290720
  • ReraGenie IDRG-GJ-78599

Builder

  • NameKEVAL VISION CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations4 more →

Key dates

this monthRegisteredJan 2018First promiseJun 2018Revised toAug 2020

Key facts

Registration and timeline

  • StatusValid until 31 Aug 2020
  • Registered on3 Jan 2018
  • Promised completion31 Aug 2020
  • Revised completionRevised to 31 Aug 2020 (originally 30 Jun 2018)
  • Buildings12 building records
  • Documents filed48 files

Current status

99%383 of 386 units booked
100.0%Of the estimated cost spent so far

Figures as on 5 Mar 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
F---28028
G---261238
A---521870
A1------
B---512475
B1------
C---54963
C1------
D---56056
D1------
E---56056
E1------

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building12

As on 5 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

108 of 108 construction stages are filed complete across 12 buildings.

F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 5 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,569 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.32 cr
Cost incurredRs 30.32 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 2.53 crRs 2.53 cr
A1NARs 2.53 crRs 2.53 cr
BNARs 2.53 crRs 2.53 cr
B1NARs 2.53 crRs 2.53 cr
CNARs 2.53 crRs 2.53 cr
C1NARs 2.53 crRs 2.53 cr
DNARs 2.53 crRs 2.53 cr
D1NARs 2.53 crRs 2.53 cr
ENARs 2.53 crRs 2.53 cr
E1NARs 2.53 crRs 2.53 cr
FNARs 2.53 crRs 2.53 cr
GNARs 2.53 crRs 2.53 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01194/EX1/290720Applied Dec 2019; approved Jul 2020

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/MAA01194/EX1/290720 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 Mar 2022
Engineer's certificate (Form 2)5 Mar 2022
Engineer's certificate annexure5 Mar 2022
Accountant's certificate (Form 3)5 Mar 2022
Site photograph, F5 Mar 2022
Site photograph, G5 Mar 2022
Site photograph, A5 Mar 2022
Site photograph, A15 Mar 2022
Site photograph, B5 Mar 2022
Site photograph, B15 Mar 2022
Site photograph, C5 Mar 2022
Site photograph, C15 Mar 2022
Site photograph, D5 Mar 2022
Site photograph, D15 Mar 2022
Site photograph, E5 Mar 2022
Site photograph, E15 Mar 2022
RERA registration certificate3 Jan 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

99%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 26 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ASHRAYA - 9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kali5,400+ in Ahmedabad

2 kmASHRAYA - 9Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 129 registered projects within 2 km.

Builder: KEVAL VISION CORPORATION

KEVAL VISION CORPORATION has 5 registrations on GujRERA, including ASHRAYA - 9 and ASHRAYA 9. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ASHRAYA - 9 is delayed beyond 31 Aug 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ASHRAYA - 9?

The registered promoter entity is KEVAL VISION CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ASHRAYA - 9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ASHRAYA - 9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHRAYA - 9. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHRAYA - 9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.