Home / Browse projects / Rajkot, Gujarat / Arise Two

Valid until 15 Jun 2022 Residential/Group Housing project

Arise Two

By Tanvi Kariya , Proprietor of Applied Ideas

RG-GJ-01428 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX2/060422 · Last updated on GujRERA portal: 15 Jun 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2022Possession promisedmoved 30 months from the original
9 of 9Construction stages doneevery applicable stage filed complete
3 of 37Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Arise Two is a Residential/Group Housing project by Tanvi Kariya , Proprietor of Applied Ideas in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX2/060422 on 19 Jun 2018. Possession is promised by 15 Jun 2022. The completion date has moved by 30 months from the original filing. 34 of the 37 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameArise Two
  • TypeResidential/Group Housing
  • Location
    • Ghanteshwar 140/2/1 Plot No. 7
    • New 150 Feet Ring Road
    • Ghanteshwar
    • Rajkot
    • 360006
  • Pincode360006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX2/060422
  • ReraGenie IDRG-GJ-01428

Builder

  • NameTanvi Kariya , Proprietor of Applied Ideas
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJun 2018First promiseDec 2019Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 15 Jun 2022
  • Registered on19 Jun 2018
  • Promised completion15 Jun 2022
  • Revised completionRevised to 15 Jun 2022 (originally 25 Dec 2019)
  • Buildings1 building record
  • Documents filed38 files

Current status

92%34 of 37 units booked
137.6%Of the estimated cost spent so far

Figures as on 15 Jun 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---37037

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 15 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

1: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 15 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,514 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.00 cr
Cost incurredRs 8.26 cr
Spent of the estimate137.6%
BuildingWingEstimatedIncurred
1NARs 6.00 crRs 8.26 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNirav Khant
EngineerKalpesh Satasiya

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX1/180220Applied Jan 2020; approved Feb 2020
PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX2/060422Applied Jan 2022; approved Apr 2022

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA02936/EX2/060422 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)15 Jun 2022
Engineer's certificate (Form 2)15 Jun 2022
Engineer's certificate annexure15 Jun 2022
Accountant's certificate (Form 3)15 Jun 2022
Site photograph, 115 Jun 2022
RERA registration certificate19 Jun 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

92%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one moved by 30 months

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep Arise Two on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ghanteshwar1,800+ in Rajkot

2 kmArise TwoOther 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: Tanvi Kariya , Proprietor of Applied Ideas

Tanvi Kariya , Proprietor of Applied Ideas has 1 registration on GujRERA, including Arise Two. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if Arise Two is delayed beyond 15 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Arise Two?

The registered promoter entity is Tanvi Kariya , Proprietor of Applied Ideas, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Arise Two?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Arise Two?

The professionals named in the filing: Architect: Nirav Khant; Engineer: Kalpesh Satasiya. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Arise Two?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Arise Two. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Arise Two to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.