Home / Browse projects / Ahmedabad, Gujarat / ANAND RESIDENCY

Valid until 31 Mar 2026 Residential/Group Housing project

ANAND RESIDENCY

By DAGA PROCON PRIVATE LIMITED

RG-GJ-25360 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA12809/240124/310326 · Last updated on GujRERA portal: 4 Sep 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2026Possession promisedno revision filed
7 of 9Construction stages donefurthest along: Plinth, 0%
1 of 15Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

ANAND RESIDENCY is a Residential/Group Housing project by DAGA PROCON PRIVATE LIMITED in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA12809/240124/310326 on 24 Jan 2024. Possession is promised by 31 Mar 2026. 14 of the 15 units on this registration are recorded sold or booked, and 7 of 9 construction stages are filed complete.

At a glance

Project

  • NameANAND RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • OPP. HEDGEWAR BHAVAN
    • BALIYAKAKA ROAD
    • KANKARIA
    • MANINAGAR
    • Ahmedabad City
    • Ahmedabad
    • 380022
  • Pincode380022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA12809/240124/310326
  • ReraGenie IDRG-GJ-25360

Builder

  • NameDAGA PROCON PRIVATE LIMITED
  • Entity typeCOMPANY

Key dates

this monthRegisteredJan 2024PromisedMar 2026

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2026
  • Registered on24 Jan 2024
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed47 files

Current status

93%14 of 15 units booked
15.9%Of the estimated cost spent so far

Figures as on 4 Sep 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---15015

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 4 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 0%.

A: 78% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 4 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area514 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.73 cr
Cost incurredRs 43.50 lakh
Spent of the estimate15.91%
BuildingWingEstimatedIncurred
ANARs 2.73 crRs 43.50 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHIRAK PRAGNESH PATEL
EngineerUTSAV SHAILESHBHAI PATEL

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/RAA12809/240124/310326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)4 Sep 2025
Architect's certificate (Form 1)2 Sep 2025
Site photograph, A2 Sep 2025
Engineer's certificate (Form 2)9 Oct 2024
Engineer's certificate annexure9 Oct 2024
RERA registration certificate24 Jan 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

93%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one has not

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep ANAND RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MANINAGAR5,400+ in Ahmedabad

2 kmANAND RESIDENCYOther 123Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: DAGA PROCON PRIVATE LIMITED

DAGA PROCON PRIVATE LIMITED has 1 registration on GujRERA, including ANAND RESIDENCY. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if ANAND RESIDENCY is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ANAND RESIDENCY?

The registered promoter entity is DAGA PROCON PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ANAND RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ANAND RESIDENCY?

The professionals named in the filing: Architect: HIRAK PRAGNESH PATEL; Engineer: UTSAV SHAILESHBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANAND RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANAND RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANAND RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.