ReraGenieLog inGet a buyer report

Home / Browse projects / Rajkot, Gujarat / AMIDHARA

Valid until 31 Dec 2023 Residential/Group Housing project

AMIDHARA

By MAHAVIR ENTERPRISE

RG-GJ-88768 · RERA PR/GJ/RAJKOT/RAJKOT/Others/RAA08160/A1R/300722 · Last updated on GujRERA portal: 14 Mar 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
24 of 27Construction stages doneacross 3 buildings; furthest along: Plinth, 0%
54 of 70Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

AMIDHARA is a Residential/Group Housing project by MAHAVIR ENTERPRISE in Rajkot, Gujarat, registered with GujRERA as PR/GJ/RAJKOT/RAJKOT/Others/RAA08160/A1R/300722 on 9 Mar 2021. Possession is promised by 31 Dec 2023. 16 of the 70 units on this registration are recorded sold or booked, and 24 of 27 construction stages are filed complete.

At a glance

Project

  • NameAMIDHARA
  • TypeResidential/Group Housing
  • Location
    • NEAR AKASHVANI CHOWK
    • BEHIND FSL
    • AYURVEDIC HOSPITAL
    • UNIVERSITY ROAD
    • Rajkot
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/RAJKOT/RAJKOT/Others/RAA08160/A1R/300722
  • ReraGenie IDRG-GJ-88768

Builder

  • NameMAHAVIR ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredMar 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2023
  • Registered on9 Mar 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed43 files

Current status

23%16 of 70 units booked
100.0%Of the estimated cost spent so far

Figures as on 14 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---28028
A---14014
C---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 14 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Plinth, at 0%.

B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 14 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,550 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.00 cr
Cost incurredRs 9.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 3.00 crRs 3.00 cr
BNARs 3.00 crRs 3.00 cr
CNARs 3.00 crRs 3.00 cr

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerC M SINGALA

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/RAJKOT/RAJKOT/Others/RAA08160/A1R/300722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)14 Mar 2024
Engineer's certificate (Form 2)14 Mar 2024
Engineer's certificate annexure14 Mar 2024
Accountant's certificate (Form 3)14 Mar 2024
Site photograph, B13 Mar 2024
Site photograph, A13 Mar 2024
Site photograph, C13 Mar 2024
RERA registration certificate9 Mar 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Rajkot

23%of this project is bookeddistrict median 56%
13%of Rajkot projects moved their completion datethis one has not

Computed across the 1,800+ Rajkot projects on ReraGenie, from their own filings.

Keep AMIDHARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Rajkot1,800+ in Rajkot

2 kmAMIDHARAOther 301Dot size: filed unitsN

Filed coordinates, straight-line distance. 301 registered projects within 2 km.

Builder: MAHAVIR ENTERPRISE

MAHAVIR ENTERPRISE has 3 registrations on GujRERA, including AMIDHARA and MAHAVEER HEIGHTS. Read the full track record. See more projects on the Rajkot district page.

Frequently asked questions

What are my rights if AMIDHARA is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AMIDHARA?

The registered promoter entity is MAHAVIR ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AMIDHARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AMIDHARA?

The professionals named in the filing: Engineer: C M SINGALA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMIDHARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMIDHARA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMIDHARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.