Valid until 30 Jun 2022 Commercial project

Alpha Business Park

By SAMKIT INFRACON

RG-GJ-34386 · RERA PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00801/EX1/150921 · Last updated on GujRERA portal: 7 Mar 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jun 2022Possession promisedmoved 12 months from the original
4 of 9Construction stages donefurthest along: Staircases, 95%
25 of 82Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

Alpha Business Park is a Commercial project by SAMKIT INFRACON in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00801/EX1/150921 on 22 Nov 2017. Possession is promised by 30 Jun 2022. The completion date has moved by 12 months from the original filing. 57 of the 82 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameAlpha Business Park
  • TypeCommercial
  • Location
    • Nr Gormoh Restaurant
    • Opp Judges Bunglow
    • Bodakdev
    • Bodakdev
    • Ahmedabad City
    • Ahmedabad
    • 380054
  • Pincode380054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00801/EX1/150921
  • ReraGenie IDRG-GJ-34386

Builder

  • NameSAMKIT INFRACON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredNov 2017First promiseJun 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2022
  • Registered on22 Nov 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed38 files

Current status

70%57 of 82 units booked
56.2%Of the estimated cost spent so far

Figures as on 7 Mar 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---08282

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

1: 79% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%

Progress on shared amenities19

As on 7 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes100%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes20%
Fire fightingYes80%
Drinking water facilitiesYes90%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,077 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 15.15 cr
Cost incurredRs 8.51 cr
Spent of the estimate56.19%
BuildingWingEstimatedIncurred
1NARs 15.15 crRs 8.51 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectADS Architect Pvt. Ltd.
EngineerBhoomi Consultants

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00801/EX1/150921Applied Jun 2021; approved Sep 2021

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/AHMEDABAD CITY/AUDA/CAA00801/EX1/150921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Mar 2022
Engineer's certificate (Form 2)7 Mar 2022
Engineer's certificate annexure7 Mar 2022
Accountant's certificate (Form 3)7 Mar 2022
Site photograph, 17 Mar 2022
RERA registration certificate22 Nov 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Ahmedabad

70%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 12 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Alpha Business Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bodakdev5,400+ in Ahmedabad

2 kmAlpha Business ParkOther 167Dot size: filed unitsN

Filed coordinates, straight-line distance. 167 registered projects within 2 km.

Builder: SAMKIT INFRACON

SAMKIT INFRACON has 1 registration on GujRERA, including Alpha Business Park. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Alpha Business Park is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Alpha Business Park?

The registered promoter entity is SAMKIT INFRACON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Alpha Business Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Alpha Business Park?

The professionals named in the filing: Architect: ADS Architect Pvt. Ltd.; Engineer: Bhoomi Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Alpha Business Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Alpha Business Park. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Alpha Business Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.