Valid until 25 Nov 2023 Commercial project

AKHILAM SQUARE

By KESHAV DEVELOPERS

RG-GJ-07639 · RERA PR/GJ/JAMNAGAR/JAMNAGAR/Others/CAA11503/210323 · Last updated on GujRERA portal: 21 Mar 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Nov 2023Possession promisedno revision filed
5 of 8Construction stages donefurthest along: Internal walls, 85%
32 of 32Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

AKHILAM SQUARE is a Commercial project by KESHAV DEVELOPERS in Jamnagar, Gujarat, registered with GujRERA as PR/GJ/JAMNAGAR/JAMNAGAR/Others/CAA11503/210323 on 21 Mar 2023. Possession is promised by 25 Nov 2023. 0 of the 32 units on this registration are recorded sold or booked, and 5 of 8 construction stages are filed complete.

At a glance

Project

  • NameAKHILAM SQUARE
  • TypeCommercial
  • Location
    • R.S. No. 1096
    • Amalgamated Plot No. 75/1
    • Ashirwad Deep - 4
    • Opp. Sangam Baug
    • Ranjitsagar Road
    • Jamnagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/JAMNAGAR/JAMNAGAR/Others/CAA11503/210323
  • ReraGenie IDRG-GJ-07639

Builder

  • NameKESHAV DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations7 more →

Key dates

this monthRegisteredMar 2023PromisedNov 2023

Key facts

Registration and timeline

  • StatusValid until 25 Nov 2023
  • Registered on21 Mar 2023
  • Promised completion25 Nov 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

0%0 of 32 units booked
97.7%Of the estimated cost spent so far

Figures as on 21 Mar 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---03232

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 8 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

A: 84% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats85%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%

Progress on shared amenities19

As on 21 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsNoNot applicable
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area579 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 39.94 lakh
Cost incurredRs 39.00 lakh
Spent of the estimate97.65%
BuildingWingEstimatedIncurred
ANARs 39.94 lakhRs 39.00 lakh

Certifying professionals and partners1

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerDHIREN NAKUM

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/JAMNAGAR/JAMNAGAR/Others/CAA11503/210323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate21 Mar 2023
Architect's certificate (Form 1)18 Feb 2023
Engineer's certificate (Form 2)18 Feb 2023
Engineer's certificate annexure18 Feb 2023
Accountant's certificate (Form 3)18 Feb 2023
Site photograph, A18 Feb 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Jamnagar

0%of this project is bookeddistrict median 24%
7%of Jamnagar projects moved their completion datethis one has not

Computed across the 220+ Jamnagar projects on ReraGenie, from their own filings.

Keep AKHILAM SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Jamnagar220+ in Jamnagar

2 kmAKHILAM SQUAREOther 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: KESHAV DEVELOPERS

KESHAV DEVELOPERS has 8 registrations on GujRERA, including Keshav Aaradhyam and KRISHNA BUSINESS HUB. Read the full track record. See more projects on the Jamnagar district page.

Frequently asked questions

What are my rights if AKHILAM SQUARE is delayed beyond 25 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AKHILAM SQUARE?

The registered promoter entity is KESHAV DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AKHILAM SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AKHILAM SQUARE?

The professionals named in the filing: Engineer: DHIREN NAKUM. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKHILAM SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKHILAM SQUARE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKHILAM SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.