Home / Browse projects / Ahmedabad, Gujarat / Akanksha

Valid until 30 Jun 2021 Residential/Group Housing project

Akanksha

By B. Nanji A

RG-GJ-10083 · RERA PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX2/010421 · Last updated on GujRERA portal: 17 Feb 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 27 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2021Possession promisedmoved 27 months from the original
144 of 168Construction stages doneacross 22 buildings; furthest along: Staircases, 90%
0 of 43Units unsoldnot recorded sold or booked
Jump to the 59 documents Report an error

Akanksha is a Residential/Group Housing project by B. Nanji A in Ahmedabad, Gujarat, registered with GujRERA as PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX2/010421 on 6 Dec 2017. Possession is promised by 30 Jun 2021. The completion date has moved by 27 months from the original filing. 43 of the 43 units on this registration are recorded sold or booked, and 144 of 168 construction stages are filed complete.

At a glance

Project

  • NameAkanksha
  • TypeResidential/Group Housing
  • Location
    • Akanksha
    • India Colony
    • Near Radhe Upvan
    • Mahemdavad Road
    • Hathijan
    • Hathian
    • Daskroi
    • Ahmedabad
    • 382445
  • Pincode382445
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX2/010421
  • ReraGenie IDRG-GJ-10083

Builder

  • NameB. Nanji A
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2017First promiseMar 2019Revised toJun 2021

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2021
  • Registered on6 Dec 2017
  • Promised completion30 Jun 2021
  • Revised completionRevised to 30 Jun 2021 (originally 31 Mar 2019)
  • Buildings22 building records
  • Documents filed59 files

Current status

100%43 of 43 units booked
93.5%Of the estimated cost spent so far

Figures as on 17 Feb 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---202
B---202
C---202
D---202
E---202
F---202
G---202
H---202
I---202
J---101
K---202
L---202
M---202
N---202
O---202
P---202
Q---202
R---202
S---202
T---202
U---202
V---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 17 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 22 buildings; the table lists the first 20.

144 of 168 construction stages are filed complete across 22 buildings. The stage furthest along is Staircases, at 90%.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
I89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
JNot stated
ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
K100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
L89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
M89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
N89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
O80%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing60%
P100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Q100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
R100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
S100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
T100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 17 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,202 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.00 cr
Cost incurredRs 11.22 cr
Spent of the estimate93.5%
BuildingWingEstimatedIncurred
ANARs 54.55 lakhRs 51.00 lakh
BNARs 54.55 lakhRs 51.00 lakh
CNARs 54.55 lakhRs 51.00 lakh
DNARs 54.55 lakhRs 51.00 lakh
ENARs 54.55 lakhRs 51.00 lakh
FNARs 54.55 lakhRs 51.00 lakh
GNARs 54.55 lakhRs 51.00 lakh
HNARs 54.55 lakhRs 51.00 lakh
INARs 54.55 lakhRs 51.00 lakh
JNARs 54.55 lakhRs 51.00 lakh
KNARs 54.55 lakhRs 51.00 lakh
LNARs 54.55 lakhRs 51.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj L Kanani
EngineerKetan K Patel

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX1/200419Applied Apr 2019; approved Apr 2019
PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX2/010421Applied Feb 2021; approved Apr 2021

Documents filed59

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/AHMEDABAD/DASKROI/AUDA/RAA00930/EX2/010421 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)17 Feb 2021
Site photograph, A17 Feb 2021
Site photograph, B17 Feb 2021
Site photograph, C17 Feb 2021
Site photograph, D17 Feb 2021
Site photograph, E17 Feb 2021
Site photograph, F17 Feb 2021
Site photograph, G17 Feb 2021
Site photograph, H17 Feb 2021
Site photograph, I17 Feb 2021
Site photograph, J17 Feb 2021
Site photograph, K17 Feb 2021
Site photograph, L17 Feb 2021
Site photograph, M17 Feb 2021
Site photograph, N17 Feb 2021
Site photograph, O17 Feb 2021
Site photograph, P17 Feb 2021
Site photograph, Q17 Feb 2021
Site photograph, R17 Feb 2021
Site photograph, S17 Feb 2021
Site photograph, T17 Feb 2021
Site photograph, U17 Feb 2021
Site photograph, V17 Feb 2021
Accountant's certificate (Form 3)2 Sep 2020
RERA registration certificate6 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Ahmedabad

100%of this project is bookeddistrict median 53%
14%of Ahmedabad projects moved their completion datethis one moved by 27 months

Computed across the 5,400+ Ahmedabad projects on ReraGenie, from their own filings.

Keep Akanksha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Hathian5,400+ in Ahmedabad

2 kmAkankshaOther 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 33 registered projects within 2 km.

Builder: B. Nanji A

B. Nanji A has 3 registrations on GujRERA, including Abhishek and Akanksha. Read the full track record. See more projects on the Ahmedabad district page.

Frequently asked questions

What are my rights if Akanksha is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Akanksha?

The registered promoter entity is B. Nanji A, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Akanksha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Akanksha?

The professionals named in the filing: Architect: Manoj L Kanani; Engineer: Ketan K Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Akanksha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Akanksha. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Akanksha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.