Valid until 31 Mar 2026 Mixed Development project

AAKAR SKY

By AAKAR BUILDCON

RG-GJ-23091 · RERA PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/MN124AA10024/200722 · Last updated on GujRERA portal: 9 Sep 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2026Possession promisedno revision filed
0 of 36Construction stages doneacross 4 buildings; furthest along: Excavation, 95%
28 of 161Units unsoldnot recorded sold or booked
Jump to the 27 documents Report an error

AAKAR SKY is a Mixed Development project by AAKAR BUILDCON in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/MN124AA10024/200722 on 20 Jul 2022. Possession is promised by 31 Mar 2026. 133 of the 161 units on this registration are recorded sold or booked, and 0 of 36 construction stages are filed complete.

At a glance

Project

  • NameAAKAR SKY
  • TypeMixed Development
  • Location
    • AAKAR SKY
    • B/H. GOKUL MERIDIAN
    • MODHERA ROAD
    • MEHSANA
    • MEHSANA
    • 384002
  • Pincode384002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/MN124AA10024/200722
  • ReraGenie IDRG-GJ-23091

Builder

  • NameAAKAR BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2022PromisedMar 2026

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2026
  • Registered on20 Jul 2022
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed27 files

Current status

83%133 of 161 units booked
68.8%Of the estimated cost spent so far

Figures as on 9 Sep 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-E---28028
BLOCK-B&C---561470
BLOCK-D---28735
BLOCK-A---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 9 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 95%.

BLOCK-E60%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt Floor54%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats57%
Sanitary fittings within the flats36%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing36%
BLOCK-B&C60%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt Floor50%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats57%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing36%
BLOCK-D62%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt Floor57%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats57%
Sanitary fittings within the flats43%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%
BLOCK-A60%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt Floor54%
Slabs of Super Structure86%
Internal walls, internal plaster, floorings, doors and windows within flats57%
Sanitary fittings within the flats36%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing36%

Progress on shared amenities23

As on 9 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes90%
Landscaping and tree plantingYes30%
Street lightingYes30%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes70%
Solid waste management and disposalYes30%
Water conservation, rain water harvestingYes85%
Energy managementYes30%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes30%
Fire fightingYes30%
Drinking water facilitiesYes20%
Emergency evacuationYes20%
Use of renewable energyYes0%
SecurityYes20%
Letter boxYes0%
Compound wallYes30%
Plinth protectionYes20%
Water tankYes20%
Other requirementsYes20%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,086 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 16.00 cr
Cost incurredRs 11.00 cr
Spent of the estimate68.75%
BuildingWingEstimatedIncurred
BLOCK-B&CNARs 6.00 crRs 4.05 cr
BLOCK-ANARs 4.00 crRs 2.75 cr
BLOCK-DNARs 3.00 crRs 2.10 cr
BLOCK-ENARs 3.00 crRs 2.10 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVANG LAXMANBHAI PATEL
EngineerSMIT PRAKASHKUMAR PATEL

Documents filed27

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/MN124AA10024/200722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)9 Sep 2024
Engineer's certificate annexure9 Sep 2024
RERA registration certificate20 Jul 2022
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

83%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one has not

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep AAKAR SKY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MEHSANA200+ in Mehsana

2 kmAAKAR SKYOther 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: AAKAR BUILDCON

AAKAR BUILDCON has 1 registration on GujRERA, including AAKAR SKY. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if AAKAR SKY is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAKAR SKY?

The registered promoter entity is AAKAR BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAKAR SKY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAKAR SKY?

The professionals named in the filing: Architect: DEVANG LAXMANBHAI PATEL; Engineer: SMIT PRAKASHKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAKAR SKY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAKAR SKY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAKAR SKY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.