Home / Browse projects / Mehsana, Gujarat / AAKAR AANGAN

Valid until 30 Mar 2027 Residential/Group Housing project

AAKAR AANGAN

By AAKAR INFRATECH

RG-GJ-36620 · RERA PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/RN306AA10206/EX1/130326/300327 · Last updated on GujRERA portal: 29 Jul 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Mar 2027Possession promisedmoved 12 months from the original
2 of 9Construction stages donefurthest along: Slabs of Super Structure, 85%
18 of 81Units unsoldnot recorded sold or booked
Jump to the 33 documents Report an error

AAKAR AANGAN is a Residential/Group Housing project by AAKAR INFRATECH in Mehsana, Gujarat, registered with GujRERA as PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/RN306AA10206/EX1/130326/300327 on 27 Feb 2023. Possession is promised by 30 Mar 2027. The completion date has moved by 12 months from the original filing. 63 of the 81 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NameAAKAR AANGAN
  • TypeResidential/Group Housing
  • Location
    • SURVEY NO. 38
    • AAKAR AANGAN
    • BEHIND GOKUL MERIDIAN
    • MODHERA ROAD
    • MEHSANA
    • NAGALPUR
    • Mehsana
    • 384002
  • Pincode384002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/RN306AA10206/EX1/130326/300327
  • ReraGenie IDRG-GJ-36620

Builder

  • NameAAKAR INFRATECH
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusValid until 30 Mar 2027
  • Registered on27 Feb 2023
  • Promised completion30 Mar 2027
  • Revised completionRevised to 30 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed33 files

Current status

78%63 of 81 units booked
85.0%Of the estimated cost spent so far

Figures as on 29 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1 TO 81 RESIDENTIAL UNITS---81081

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

1 TO 81 RESIDENTIAL UNITS: 66% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats60%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes60%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes90%
Landscaping and tree plantingYes50%
Street lightingYes60%
Community buildingsYes60%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalYes60%
Water conservation, rain water harvestingYes90%
Energy managementYes60%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes60%
Fire fightingYes60%
Drinking water facilitiesYes60%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes50%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,754 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 20.00 cr
Cost incurredRs 17.00 cr
Spent of the estimate85.0%
BuildingWingEstimatedIncurred
1 TO 81 RESIDENTIAL UNITSNARs 20.00 crRs 17.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVANG LAXMANBHAI PATEL
EngineerSMIT PRAKASHKUMAR PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/RN306AA10206/EX1/130326/300327Applied Feb 2026; approved Mar 2026

Documents filed33

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/MEHSANA/MEHSANA/Mahesana Municipality/RN306AA10206/EX1/130326/300327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)29 Jul 2026
Engineer's certificate (Form 2)29 Jul 2026
Engineer's certificate annexure29 Jul 2026
Accountant's certificate (Form 3)29 Jul 2026
Site photograph, 1 TO 81 RESIDENTIAL UNITS28 Jul 2026
RERA registration certificate27 Feb 2023
Extension certificate-
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Mehsana

78%of this project is bookeddistrict median 54%
11%of Mehsana projects moved their completion datethis one moved by 12 months

Computed across the 200+ Mehsana projects on ReraGenie, from their own filings.

Keep AAKAR AANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near NAGALPUR200+ in Mehsana

2 kmAAKAR AANGANOther 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: AAKAR INFRATECH

AAKAR INFRATECH has 1 registration on GujRERA, including AAKAR AANGAN. Read the full track record. See more projects on the Mehsana district page.

Frequently asked questions

What are my rights if AAKAR AANGAN is delayed beyond 30 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAKAR AANGAN?

The registered promoter entity is AAKAR INFRATECH, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAKAR AANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAKAR AANGAN?

The professionals named in the filing: Architect: DEVANG LAXMANBHAI PATEL; Engineer: SMIT PRAKASHKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAKAR AANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAKAR AANGAN. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAKAR AANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.