Yogeshwar Realty: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Yogeshwar Realty has 8 registrations in this build, including Shivalik Sky and SHIVALIK SANKALP. Its filings disclose 7 earlier MahaRERA projects: 7 of 7 past projects completed on time.

8Registrations in this build
7Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Shivalik SkyNashik, Maharashtra--Completed
SHIVALIK SANKALPNashik, Maharashtra--Completed
SHIVALIK SIGMANashik, Maharashtra--Completed
SHIVALIK SPARSH 2Nashik, Maharashtra--Completed
SHIVALIK SKYPARKNashik, Maharashtra--Completed
Shivalik SiddhiNashik, Maharashtra--Completed
Shivalik Sankul ApartmentNashik, Maharashtra--Registration lapsed
Shivalik SkygreenNashik, Maharashtra19847%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Shivalik Sky
P51600014843
30 Dec 202327 Mar 2019On time
SHIVALIK SANKALP
P51600020755
30 Dec 20251 Mar 2021On time
SHIVALIK SIGMA
P51600021505
30 Dec 202523 Aug 2021On time
SHIVALIK SPARSH 2
P51600022262
30 Dec 202530 Jul 2021On time
Shivalik Sankul Apartment
P51600032097
31 Dec 202522 Mar 2024On time
Shivalik Siddhi
P51600028479
30 Sep 20261 Nov 2023On time
SHIVALIK SKYPARK
P51600025573
30 Sep 202627 Jul 2024On time

Frequently asked questions

How do I verify Yogeshwar Realty as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Yogeshwar Realty?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.