ReraGenieLog inGet a buyer report

Home / Developers / VASTUSHODH INFRASTRUCTURE LLP

VASTUSHODH INFRASTRUCTURE LLP: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

VASTUSHODH INFRASTRUCTURE LLP has 6 registrations in this build, including ANANDGRAM BHANDGAON BUILDING A and ANANDGRAM BHANDGAON BUILDING B. Its filings disclose 4 earlier MahaRERA projects: 0 of 4 past projects completed on time.

6Registrations in this build
4Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
ANANDGRAM BHANDGAON BUILDING APune, Maharashtra--Registration lapsed
ANANDGRAM BHANDGAON BUILDING BPune, Maharashtra--Registration lapsed
ANANDGRAM BHANDGAON BUILDING R1 AND R2Pune, Maharashtra--Registration lapsed
ANANDGRAM BHANDGAON BUILDING F1Pune, Maharashtra--Registration lapsed
ANANDGRAM BHANDGAON BUILDING F2Pune, Maharashtra--Registration lapsed
ANADGRAM BHANDGAON BUILDING GPune, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
URBANGRAM KONDHWE DHAWADE PHASE I
31 Jan 20147 Apr 2014+2 months
ANANDGRAM TALEGAON DHAMDHERE
30 Jun 201410 Oct 2014+3 months
URBANGRAM KIRKITWADI
30 Jun 201412 Feb 2015+7 months
ANADGRAM YAVAT
31 Dec 20143 Mar 2015+2 months

Frequently asked questions

How do I verify VASTUSHODH INFRASTRUCTURE LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with VASTUSHODH INFRASTRUCTURE LLP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.