Home / Developers / VARDHAMAN ASSOCIATES
VARDHAMAN ASSOCIATES: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
VARDHAMAN ASSOCIATES has 4 registrations on MahaRERA, including VARDHAMAN RESIDENCY and SAI VIDHI. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time.
Projects by this developer
Showing all 4 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| VARDHAMAN SKYTOWNP52100047530 | RAHATANI, Pune, 411017 | 400 | 92% | 7 Nov 2022 | Registered |
| SAI VIDHIP52100012531 | Pune (M Corp.), Pune, 411011 | - | - | 1 Sep 2017 | Completed |
| Vardhaman MoonstoneP52100023184 | Tathwade, Pune, 411033 | - | - | 5 Dec 2019 | Completed |
| VARDHAMAN RESIDENCYP52100001375 | Wakad, Pune, 411057 | - | - | 27 Jul 2017 | Completed |
What this promoter declares as its own experience
VARDHAMAN ASSOCIATES declares experience on 4 earlier projects. One carries a registration number we could match on MahaRERA, and it is registered under a different promoter name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
| Declared project | Registered to | Status |
|---|---|---|
| VARDHAMAN ALTEZZA | SHREE VARDHAMAN ASSOCIATES | Registered |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Vardhaman Aangan | 24 Apr 2017 | 1 Oct 2017 | +5 months |
| VARDHAMAN RESIDENCY | 1 Jan 2018 | 31 Mar 2018 | +3 months |
| Vardhaman Residency | 31 Dec 2018 | 31 Mar 2018 | On time |
| VARDHAMAN ALTEZZA P52100056423 | 30 Jun 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify VARDHAMAN ASSOCIATES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VARDHAMAN ASSOCIATES?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.