United Builders: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

United Builders has 6 registrations in this build, including United Shalimar Phase 2 and United Sanskruti Phase I. Its filings disclose 4 earlier MahaRERA projects: 0 of 4 past projects completed on time.

6Registrations in this build
4Past projects disclosed
+8 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
United Shalimar Phase 2Nashik, Maharashtra--Registration lapsed
United Sanskruti Phase INashik, Maharashtra--Completed
United Courtyard Phase INashik, Maharashtra--Completed
MARATHON ZAVER ARCADEMumbai Suburban, Maharashtra--Completed
United Courtyard Phase 2Nashik, Maharashtra--Completed
UNITED GARDENRaigarh, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
United Palms Phase I
31 Dec 201114 Aug 2014+31 months
United Palazzo
31 Jul 201229 Nov 2012+4 months
United Sharan
30 Jun 201316 Jun 2014+12 months
United Shalimar Phase I
30 Dec 20151 Feb 2016+1 months

Frequently asked questions

How do I verify United Builders as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with United Builders?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.