SHRIDHAR BHIMRAO GAIKWAD: RERA track record
Individual ยท attribution by exact filing name, entity resolution in progress
SHRIDHAR BHIMRAO GAIKWAD has 1 registration in this build, including SWARAJ ARCADE. Its filings disclose 1 earlier MahaRERA project: 0 of 1 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SWARAJ ARCADE | Pune, Maharashtra | - | - | Registration lapsed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| THE INSPIRA | 31 Dec 2018 | 31 Dec 2019 | +12 months |
Frequently asked questions
How do I verify SHRIDHAR BHIMRAO GAIKWAD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHRIDHAR BHIMRAO GAIKWAD?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.