Shree Samarth Developers has 18 registrations in this build, including Samarth Siddhi and PEARL RESIDENCY. Its filings disclose 8 earlier MahaRERA projects: 6 of 7 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Samarth Siddhi | Pune, Maharashtra | - | - | Completed |
| PEARL RESIDENCY | Pune, Maharashtra | - | - | Completed |
| Tai-Nana Sadan | Thane, Maharashtra | - | - | Completed |
| Samarth Vishwa | Pune, Maharashtra | - | - | Completed |
| SAMARTH CLASSIC | Pune, Maharashtra | - | - | Registration lapsed |
| NIRAJ RIVIERA - SHIRISH | Thane, Maharashtra | - | - | Completed |
| SHREE SAMARTH SANKUL PHASE-2 | Ratnagiri, Maharashtra | - | - | Registration lapsed |
| Shree Samarth Aashray | Raigarh, Maharashtra | - | - | Completed |
| SWAMINI HEIGHTS | Pune, Maharashtra | - | - | Registration lapsed |
| PUSHPARANG RESIDENCY | Maharashtra | - | - | Completed |
| THE BENCHMARK | Pune, Maharashtra | - | - | Registered |
| Snehashree | Thane, Maharashtra | - | - | Completed |
| JADHAV GADH | Thane, Maharashtra | - | - | Completed |
| VALKU HERITAGE | Thane, Maharashtra | - | - | Registration revoked |
| SHUBHAM KRUPA | Thane, Maharashtra | - | - | Registration lapsed |
| SWAMI MAHIMA | Raigarh, Maharashtra | - | - | Registered |
| JADHAV GADH BUILDING 2 | Thane, Maharashtra | - | - | Registered |
| Raman Legacy | Pune, Maharashtra | - | - | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| NIRAJ CITY | 29 May 2015 | 29 May 2015 | On time |
| Shree Samarth Sankul | 18 Aug 2017 | 18 Aug 2017 | On time |
| INDUS INTERNATIONAL SCHOOL | 1 Dec 2018 | 15 Jan 2019 | +1 months |
| JOG EDUCATION TRUST | 1 Dec 2019 | 1 Dec 2019 | On time |
| Niraj Riviera - Shirish | 31 Dec 2020 | 12 Oct 2020 | On time |
| JADHAV GADH | 31 Dec 2022 | 11 Apr 2022 | On time |
| NIRAJ CITY PHASE II | 22 Jul 2023 | 22 Jul 2016 | On time |
| THE BENCHMARK P52100032247 | 30 Nov 2026 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Shree Samarth Developers as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Shree Samarth Developers?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.