SHREE RIDDHI SIDDHI CONSTRUCTIONS has 16 registrations on MahaRERA, including ADINATH AURA and ADINATH ARADHANA. Its filings disclose 7 earlier MahaRERA projects: declares 3 of 6 past projects completed on time.

16RERA registrations
7Past projects disclosed
+7 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when SHREE RIDDHI SIDDHI CONSTRUCTIONS registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 16 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Adinath CrystalPM1270002500632Panvel, Raigarh, 4102061119%22 Aug 2025Registered
Adinath SolitairePM1270002500826Sector -8 Pushpak, Raigarh, 4102067612%17 Sep 2025Registered
ADINATH REVAP52000077233PUSHPAK NODE, VAHAL, Raigarh, 4102063617%31 Jul 2024Registered
ADINATH AKRUTIP52000023998PUSHPAK NODE VAHAL, Raigarh, 410206--14 Jan 2020Completed
ADINATH AMBERP52000023972PUSHPAK, VAHAL NODE, Raigarh, 410206--14 Jan 2020Completed
ADINATH ANMOLP52000046420PUSHPAK, VADGHAR NODE, Raigarh, 410206--22 Jun 2022Completed
ADINATH ARADHANAP52000014700SECTOR 2A, Raigarh, 410206--26 Dec 2017Completed
ADINATH ARCHANAP52000046340PUSHPAK, VAHAL NODE, Raigarh, 410206--22 Jun 2022Completed
ADINATH ASTHAP52000014792SECTOR-2A, Raigarh, 410206--2 Jan 2018Completed
ADINATH AURAP51700007724Kamothe, Raigarh, 410209--17 Aug 2017Completed
ADINATH GANGAP52000023191PUSHPAK NODE VAHAL, Raigarh, 410206--5 Dec 2019Completed
ADINATH NAMANP52000023845PUSHPAK, VAHAL NODE, Raigarh, 410206--7 Jan 2020Completed
ADINATH SAGARP52000023211PUSHPAK NODE VAHAL, Raigarh, 410206--6 Dec 2019Completed
ADINATH SANSKRUTIP52000024112PUSHPAK, VADGHAR NODE, Raigarh, 410206--21 Jan 2020Completed
ADINATH SRUSHTIP52000023979PUSHPAK, VADGHAR NODE, Raigarh, 410206--14 Jan 2020Completed
ADINATH VANDANP52000032190PUSHPAK, VAHAL NODE, Raigarh, 410206--14 Dec 2021Completed

What this promoter declares as its own experience

SHREE RIDDHI SIDDHI CONSTRUCTIONS declares experience on 7 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.

One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
ADINATH HOME
21 May 201228 Aug 2014+27 months
ADINATH HOMES
31 Dec 201228 Aug 2014+20 months
ADINATH ARPAN
31 Mar 201525 May 2016+14 months
ADINATH AURA
31 Dec 201719 Dec 2017On time
ADINATH GANGA
31 Dec 20222 Sep 2021On time
ADINATH SAGAR
31 Dec 20221 Sep 2021On time
Adinath Crystal
PM1270002500632
31 Dec 2028Not completed yetOngoing

Frequently asked questions

How do I verify SHREE RIDDHI SIDDHI CONSTRUCTIONS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SHREE RIDDHI SIDDHI CONSTRUCTIONS?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the SHREE RIDDHI SIDDHI CONSTRUCTIONS developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.