SHREE RIDDHI SIDDHI CONSTRUCTIONS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SHREE RIDDHI SIDDHI CONSTRUCTIONS has 16 registrations in this build, including ADINATH AURA and ADINATH ARADHANA. Its filings disclose 7 earlier MahaRERA projects: 3 of 6 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| ADINATH AURA | Raigarh, Maharashtra | - | - | Completed |
| ADINATH ARADHANA | Raigarh, Maharashtra | - | - | Completed |
| ADINATH ASTHA | Raigarh, Maharashtra | - | - | Completed |
| ADINATH GANGA | Raigarh, Maharashtra | - | - | Completed |
| ADINATH SAGAR | Raigarh, Maharashtra | - | - | Completed |
| ADINATH NAMAN | Raigarh, Maharashtra | - | - | Completed |
| ADINATH AKRUTI | Raigarh, Maharashtra | - | - | Completed |
| ADINATH SRUSHTI | Raigarh, Maharashtra | - | - | Completed |
| ADINATH AMBER | Raigarh, Maharashtra | - | - | Completed |
| ADINATH SANSKRUTI | Raigarh, Maharashtra | - | - | Completed |
| ADINATH VANDAN | Raigarh, Maharashtra | - | - | Completed |
| ADINATH ARCHANA | Raigarh, Maharashtra | - | - | Completed |
| ADINATH ANMOL | Raigarh, Maharashtra | - | - | Completed |
| ADINATH REVA | Raigarh, Maharashtra | 36 | 17% | Registered |
| Adinath Crystal | Raigarh, Maharashtra | 111 | 9% | Registered |
| Adinath Solitaire | Raigarh, Maharashtra | 76 | 12% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| ADINATH HOME | 21 May 2012 | 28 Aug 2014 | +27 months |
| ADINATH HOMES | 31 Dec 2012 | 28 Aug 2014 | +20 months |
| ADINATH ARPAN | 31 Mar 2015 | 25 May 2016 | +14 months |
| ADINATH AURA | 31 Dec 2017 | 19 Dec 2017 | On time |
| ADINATH GANGA | 31 Dec 2022 | 2 Sep 2021 | On time |
| ADINATH SAGAR | 31 Dec 2022 | 1 Sep 2021 | On time |
| Adinath Crystal PM1270002500632 | 31 Dec 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify SHREE RIDDHI SIDDHI CONSTRUCTIONS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHREE RIDDHI SIDDHI CONSTRUCTIONS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.