SAMBHAV CORPORATION: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SAMBHAV CORPORATION has 3 registrations in this build, including DEEP DEVASHREE-2 and DEEP DESIRE. Its filings disclose 25 earlier MahaRERA projects: 20 of 25 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| DEEP DEVASHREE-2 | Raigarh, Maharashtra | - | - | Completed |
| DEEP DESIRE | Raigarh, Maharashtra | - | - | Completed |
| DEEP JEWEL | Raigarh, Maharashtra | - | - | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| SHREE GANESH | 3 Nov 2014 | 16 Aug 2013 | On time |
| Shree ganesh | 3 Nov 2014 | 16 Aug 2013 | On time |
| DEEP SHIVAM | 21 Dec 2014 | 24 Feb 2015 | +2 months |
| Deep shivam | 21 Dec 2014 | 24 Feb 2015 | +2 months |
| JAI PLAZA | 16 Feb 2015 | 23 Jun 2015 | +4 months |
| Jai plaza | 16 Feb 2015 | 23 Jun 2015 | +4 months |
| JAI SAMBHAV LK PLANET | 3 Nov 2015 | 16 Sep 2014 | On time |
| Jai Sambhav Lk Planet | 3 Nov 2015 | 14 Sep 2016 | +10 months |
| BAL GANESH | 22 Jan 2016 | 28 Feb 2014 | On time |
| ARUNA SHIVAM | 28 Aug 2016 | 30 Oct 2015 | On time |
| Aruna shivam | 28 Aug 2016 | 30 Oct 2015 | On time |
| NEAL SHIVAM | 15 Jan 2017 | 23 Aug 2016 | On time |
Frequently asked questions
How do I verify SAMBHAV CORPORATION as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SAMBHAV CORPORATION?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.