Home / Developers / SAI PROVISO DEVELOPERS

SAI PROVISO DEVELOPERS: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

SAI PROVISO DEVELOPERS has 1 registration in this build, including SAI PROVISO - AASHLESHA. Its filings disclose 6 earlier MahaRERA projects: 4 of 6 past projects completed on time.

1Registrations in this build
6Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
SAI PROVISO - AASHLESHAThane, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
GALAXY NEBULA
30 Jun 201331 Jul 2013+1 months
GALAXY ORION
31 Dec 201325 Jul 2013On time
PROVISO COMPLEX
30 Sep 201418 Jul 2013On time
CARINA
31 Dec 201521 May 2015On time
PROVISO HEIGHTS
30 Jun 201631 May 2016On time
PROVISO CORNER
30 Jun 201622 Aug 2016+2 months

Frequently asked questions

How do I verify SAI PROVISO DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SAI PROVISO DEVELOPERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.