S RAHEJA LA EM LLP: RERA track record

Others ยท attribution by exact filing name, entity resolution in progress

S RAHEJA LA EM LLP has 1 registration in this build, including LA EM By S Raheja. Its filings disclose 8 earlier MahaRERA projects: 3 of 8 past projects completed on time.

1Registrations in this build
8Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
LA EM By S RahejaMumbai Suburban, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Raheja Prime
31 Jan 201430 Apr 2014+3 months
Hari Bhuvan
31 Aug 201530 Sep 2015+1 months
Natraj Madhu Park
31 Oct 201631 Aug 2016On time
Gurukripa Kalina Naphanagar CHS Ltd
31 Oct 201631 Oct 2016On time
Santacruz Sapphire CHS Ltd
1 Apr 201731 Jul 2017+4 months
Shree Pooja VII
1 Nov 20171 Feb 2018+3 months
SDS Raheja Residency LLP
31 Jan 201831 Mar 2018+2 months
Hinduja Hospita S-2
31 Dec 201831 Dec 2018On time

Frequently asked questions

How do I verify S RAHEJA LA EM LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with S RAHEJA LA EM LLP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.