Runwal Apartments Private Limited has 1 registration in this build, including RUNWAL GREENS Wings 5 - 8. Its filings disclose 6 earlier MahaRERA projects: 0 of 6 past projects completed on time.

1Registrations in this build
6Past projects disclosed
+9 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
RUNWAL GREENS Wings 5 - 8Mumbai Suburban, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Chestnut
31 Jan 20169 Mar 2016+1 months
Runwal Greens Wing B
31 Mar 201618 Mar 2017+12 months
Runwal Greens Wing A
31 May 20165 Jun 2017+12 months
R-Galleria
30 Jun 201628 Jul 2016+1 months
Runwal Greens Wing C
31 Dec 201622 Aug 2017+8 months
Runwal Greens Wing D
31 Dec 20162 Nov 2017+10 months

Frequently asked questions

How do I verify Runwal Apartments Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Runwal Apartments Private Limited?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.