ReraGenieLog inGet a buyer report

Home / Developers / RAMESH BUILDERS

RAMESH BUILDERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

RAMESH BUILDERS has 1 registration in this build, including 41 GRANDSTAND. Its filings disclose 4 earlier MahaRERA projects: 2 of 3 past projects completed on time.

1Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
41 GRANDSTANDMumbai City, Maharashtra258%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
HERMES PARAS - 6
31 Dec 199231 Dec 1993+12 months
HERMES KUNJ
31 Dec 199331 Dec 1993On time
HERMES PALAZZO
8 Nov 199911 Aug 1999On time
41 GRANDSTAND
P51900079615
30 Jun 2029Not completed yetOngoing

Frequently asked questions

How do I verify RAMESH BUILDERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RAMESH BUILDERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.