RAJKOT MUNICIPAL CORPORATION has 35 registrations on GujRERA, including construction of 168 EWS units and Smart Ghar 1.

35RERA registrations

Projects by this developer

Showing all 35 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Rajkot Municipal Corporation Smart Ghar 5 and 6PR/GJ/RAJKOT/RAJKOT/Others/MAA10360/270622Rajkot21930%27 Jun 2022Valid until 31 Mar 2023
West Zone Package 5-15A & 28APR/GJ/RAJKOT/RAJKOT/Others/MAA07547/121020Vavdi, Rajkot129890%12 Oct 2020Valid until 1 Feb 2024
Smart Ghar 3PR/GJ/RAJKOT/RAJKOT/Others/MAA03327/300818Mavdi, Rajkot, 36000512100%30 Aug 2018Valid until 31 Dec 2019
GHTC-I LHP RajkotPR/GJ/RAJKOT/RAJKOT/Others/MAA07456/150920Raiya, Rajkot115896%15 Sep 2020Valid until 1 Sep 2022
West Zone Package 3 -FP 41APR/GJ/RAJKOT/RAJKOT/Others/MAA06357/201119Mavdi, Rajkot90882%20 Nov 2019Valid until 30 Mar 2023
Central Package 1 -FP 12BPR/GJ/RAJKOT/RAJKOT/Others/MAA12280/010923Rajkot74791%1 Sep 2023Valid until 30 Apr 2027
West Zone Package 5-51BPR/GJ/RAJKOT/RAJKOT/Others/MAA07560/191020Vavdi, Rajkot68085%19 Oct 2020Valid until 1 Feb 2024
Smart Ghar 2PR/GJ/RAJKOT/RAJKOT/Others/MAA03340/310818Mavdi, Rajkot, 36000566494%31 Aug 2018Valid until 30 Dec 2021
PMAY - Smart Ghar 4PR/GJ/RAJKOT/RAJKOT/Others/MAA03326/EX2/280222Rajkot, Rajkot, 3600035550%30 Aug 2018Valid until 30 Dec 2022
West Zone Package 1 -FP S2PR/GJ/RAJKOT/RAJKOT/Others/MAA06354/201119Rajkot, Rajkot48263%20 Nov 2019Valid until 30 Mar 2023
construction of 462 EWS unitsPR/GJ/RAJKOT/RAJKOT/Others/MAA03325/300818Rajkot, Rajkot, 360003480-30 Aug 2018Valid until 31 Mar 2019
West Zone Package 5-51B MavdiPR/GJ/RAJKOT/RAJKOT/Others/MAA07546/121020Rajkot, Rajkot46089%12 Oct 2020Valid until 1 Feb 2024
West Zone Package 6 - 38/APR/GJ/RAJKOT/RAJKOT/Others/RAA07519/071020Mavdi, Rajkot42095%7 Oct 2020Valid until 1 Feb 2024
Smart Ghar 1PR/GJ/RAJKOT/RAJKOT/Others/MAA03396/110918Mavdi, Rajkot, 3600044105%11 Sep 2018Valid until 31 Dec 2019
CONSTRUCTION OF 322 EWS DUSPR/GJ/RAJKOT/RAJKOT/Others/MAA03395/110918Rajkot, Rajkot, 360003356-11 Sep 2018Valid until 31 Mar 2019
Central Zone Package 1 -FP 12APR/GJ/RAJKOT/RAJKOT/Others/RAA12282/010923Rajkot31098%1 Sep 2023Valid until 30 Apr 2027
Construction of 308 EWSPR/GJ/RAJKOT/RAJKOT/Others/RAA03329/300818Rajkot, Rajkot, 360003308-30 Aug 2018Valid until 31 Dec 2019
CONSTRUCTION OF 308 EWS DUSPR/GJ/RAJKOT/RAJKOT/Others/MAA03331/300818Rajkot, Rajkot, 36000130894%30 Aug 2018Valid until 31 Dec 2019
West Zone Package 1 -FP 104PR/GJ/RAJKOT/RAJKOT/Others/RAA06356/201119Nana Mava, Rajkot28892%20 Nov 2019Valid until 30 Mar 2023
West Zone Package 1 -FP 348PR/GJ/RAJKOT/RAJKOT/Others/MAA06322/131119Nanamava, Rajkot28576%13 Nov 2019Valid until 30 Mar 2023
West Zone Package 3 -FP 48APR/GJ/RAJKOT/RAJKOT/Others/RAA06330/161119Mavdi, Rajkot27257%16 Nov 2019Valid until 30 Mar 2023
West Zone Package 1 -FP 446PR/GJ/RAJKOT/RAJKOT/Others/RAA06365/211119Nana Mava, Rajkot224100%21 Nov 2019Valid until 30 Mar 2023
West Zone Package 6 - 39/APR/GJ/RAJKOT/RAJKOT/Others/RAA07517/071020Mavdi, Rajkot22099%7 Oct 2020Valid until 1 Feb 2024
West Zone Package 2 - 3APR/GJ/RAJKOT/RAJKOT/Others/RAA06641/180120Mavdi, Rajkot21096%18 Jan 2020Valid until 30 Mar 2023
West Zone Package 6 - 33/APR/GJ/RAJKOT/RAJKOT/Others/RAA07518/071020Mavdi, Rajkot20095%7 Oct 2020Valid until 1 Feb 2024
CONSTRUCTION OF 168 EWS DUSPR/GJ/RAJKOT/RAJKOT/Others/MAA03330/300818Rajkot, Rajkot, 360004196-30 Aug 2018Valid until 31 Mar 2019
construction of 168 EWS unitsPR/GJ/RAJKOT/RAJKOT/Others/MAA03328/300818Rajkot, Rajkot, 360003186-30 Aug 2018Valid until 31 Mar 2019
West Zone Package 1 -FP S3PR/GJ/RAJKOT/RAJKOT/Others/RAA06355/201119Rajkot, Rajkot18098%20 Nov 2019Valid until 30 Mar 2023
West Zone Package 6 - 37/BPR/GJ/RAJKOT/RAJKOT/Others/RAA07522/071020Mavdi, Rajkot18098%7 Oct 2020Valid until 1 Feb 2024
Smart Ghar 4B: Construction of 128 EWS Unit (SEWS) under PMAYPR/GJ/RAJKOT/RAJKOT/Others/RAA03339/310818Rajkot, Rajkot, 3600031280%31 Aug 2018Valid until 30 Dec 2021
West Zone Package 2 - 57/1PR/GJ/RAJKOT/RAJKOT/Others/RAA06703/290120Mota Mava, Rajkot11297%29 Jan 2020Valid until 30 Mar 2023
West Zone Package 2 -6APR/GJ/RAJKOT/RAJKOT/Others/RAA06728/010220Rajkot, Rajkot10494%1 Feb 2020Valid until 30 Mar 2023
West Zone Package 2 - 2BPR/GJ/RAJKOT/RAJKOT/Others/RAA06638/170120Mavdi, Rajkot8496%17 Jan 2020Valid until 30 Mar 2023
Arvind ManiyarPR/GJ/RAJKOT/RAJKOT/Rajkot Municipal Corporation/RAA17086/080726/311227Rajkot, Rajkot, 360005760%8 Jul 2026Valid until 31 Dec 2027
West Zone Package 2 - 57/2PR/GJ/RAJKOT/RAJKOT/Others/RAA06729/010220Mota Mava, Rajkot32100%1 Feb 2020Valid until 30 Mar 2023

Frequently asked questions

How do I verify RAJKOT MUNICIPAL CORPORATION as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's GujRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RAJKOT MUNICIPAL CORPORATION?

Check the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest for every month of delay at the rate the state's RERA rules prescribe, or an exit with a full refund with interest.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official GujRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the RAJKOT MUNICIPAL CORPORATION developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.