Rajhans Infracon (India) Private Limited: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Rajhans Infracon (India) Private Limited has 1 registration in this build, including Rajhans Helix 3. Its filings disclose 7 earlier MahaRERA projects: 0 of 7 past projects completed on time.

1Registrations in this build
7Past projects disclosed
+6 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Rajhans Helix 3Mumbai Suburban, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Rajhans Ornate
31 Mar 201424 Nov 2014+8 months
Rajhans Orange
30 Jun 201416 Jan 2015+7 months
Rajhans Otium
15 Oct 201528 Sep 2016+11 months
Rajhans Belizza - I
1 Jan 201624 Jun 2016+6 months
Rajhans Belliza - II
1 Jan 201624 Jun 2016+6 months
Rajhans Zion
9 Feb 20167 Apr 2016+2 months
Rajhans Cosmic
15 Feb 201622 Jul 2016+5 months

Frequently asked questions

How do I verify Rajhans Infracon (India) Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Rajhans Infracon (India) Private Limited?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.