ReraGenieLog inGet a buyer report

Home / Developers / PUSHP GANGA PROPERTIES

PUSHP GANGA PROPERTIES: RERA track record

GSTIN 27AAMFP1275E1Z6 · Partnership · attribution by exact filing name, entity resolution in progress

PUSHP GANGA PROPERTIES has 1 registration in this build, including POOJA ENCLAVE. Its filings disclose 1 earlier MahaRERA project: 0 of 1 past projects completed on time.

1Registrations in this build
1Past projects disclosed
+12 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
POOJA ENCLAVEPune, Maharashtra880%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Ganga Paritosh B
1 Jan 202131 Dec 2021+12 months

Frequently asked questions

How do I verify PUSHP GANGA PROPERTIES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAMFP1275E1Z6 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PUSHP GANGA PROPERTIES?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.