ReraGenieLog inGet a buyer report

Home / Developers / PRIME HOMES

PRIME HOMES: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

PRIME HOMES has 3 registrations in this build, including PRIME HOMES and PRIME EXOTICA. Its filings disclose 3 earlier MahaRERA projects: 3 of 3 past projects completed on time. Litigation is declared on 1 of its registrations.

3Registrations in this build
3Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
PRIME HOMESRaigarh, Maharashtra--Completed
PRIME EXOTICARaigarh, Maharashtra--Completed
Prime HorizonRaigarh, Maharashtra4912%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
PRIME HOMES
31 Dec 20194 May 2019On time
PRIME HOMES
P52000005213
30 Dec 20224 May 2019On time
PRIME EXOTICA
P52000022840
28 Aug 202315 Sep 2022On time

Frequently asked questions

How do I verify PRIME HOMES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PRIME HOMES?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make PRIME HOMES unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.