PARANJPE DEVELOPERS LLP has 1 registration in this build, including Dinkar Apartments. Its filings disclose 3 earlier MahaRERA projects: 0 of 3 past projects completed on time.

1Registrations in this build
3Past projects disclosed
+21 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Dinkar ApartmentsPune, Maharashtra80%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Shree Apartments
24 Jun 20225 Jan 2024+18 months
Mohini- Madhav
19 Oct 202231 Jul 2024+21 months
Pushkraj
26 May 202327 Mar 2025+22 months

Frequently asked questions

How do I verify PARANJPE DEVELOPERS LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27ABDFP3367M1ZR on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PARANJPE DEVELOPERS LLP?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.