Home / Developers / NILESH MADHUKAR JADHAV
NILESH MADHUKAR JADHAV: RERA track record
Individual ยท attribution by exact filing name, entity resolution in progress
NILESH MADHUKAR JADHAV has 1 registration in this build, including JADHAV PARK. Its filings disclose 3 earlier MahaRERA projects: 3 of 3 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| JADHAV PARK | Nashik, Maharashtra | - | - | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Sai Apartment | 1 Dec 2015 | 1 Dec 2015 | On time |
| Sai Krupa | 7 Aug 2017 | 7 Aug 2017 | On time |
| JADHAV PARK P51600025514 | 29 Nov 2025 | 25 Mar 2025 | On time |
Frequently asked questions
How do I verify NILESH MADHUKAR JADHAV as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with NILESH MADHUKAR JADHAV?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.