Nashik Housing And Area Development Board: RERA track record
Public Authority ยท attribution by exact filing name, entity resolution in progress
Nashik Housing And Area Development Board has 14 registrations on MahaRERA, including Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon and CONSTRUCTION OF 16 SHOPS 48 MIG TS 32 LIG TS. Its filings disclose 11 earlier MahaRERA projects: declares 7 of 11 past projects completed on time.
Projects by this developer
Showing all 14 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Tranquility TowerPM1220002500780 | Adgaon, Nashik, 423101 | 83 | 0% | 15 Sep 2025 | Registered |
| Gulmohar GardenPM1220002500374 | Pathardi phata, Nashik, 422010 | 37 | 0% | 28 Jul 2025 | Registered |
| Parkside PalmsPR1220002500641 | Pathardi, Nashik, 422010 | 35 | 0% | 25 Aug 2025 | Registered |
| Acacia apartmentPR1220002500863 | Boys Hostel, Adgaon, Nashik, 423101 | 20 | 0% | 22 Sep 2025 | Registered |
| Starlight sanctuaryPM1220002500864 | Jatra Hotel, Adgaon, Nashik, 423101 | 18 | 0% | 22 Sep 2025 | Registered |
| CONSTRUCTION OF 12 TS LIG AND 12 TS MIG AT S NO 212 P AT MHASRUL NASHIKP51600023968 | OPP RELIANCE PETROL PUMP, Nashik, 422004 | - | - | 14 Jan 2020 | Completed |
| CONSTRUCTION OF 154 TS EWS I AND 24 TS EWS II TOTAL 178 TS ON S NO 36/B/1 AT KAMATHWADE NASHIKP51600019848 | KAMATHWADE, Nashik, 422008 | - | - | 5 Mar 2019 | Completed |
| CONSTRUCTION OF 16 SHOPS 48 MIG TS 32 LIG TSP51600012853 | 422007 | - | - | 7 Sep 2017 | Completed |
| CONSTRUCTION OF 175 TS EWS UNDER PMAY AND 33 SHOPS ON G NO602/2 ADGAON NASHIKP51600026501 | ADGAON-MHASRUL LINK ROAD ADGAON, Nashik, 422003 | - | - | 26 Sep 2020 | Registration lapsed |
| Construction of 30 HIG T/s. on plots of S. No. 299/1C and 299/2 at Sakegaon, Bhusawal, Dist. JalgaonP49900010896 | Sakegaon, Jalgaon, 425201 | - | - | 31 Aug 2017 | Registration lapsed |
| Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. JalgaonP49900007208 | Sakegaon, Jalgaon, 425201 | - | - | 17 Aug 2017 | Completed |
| CONSTRUCTION OF 448 TS EWS UNDER PMAY AND 32 SHOPSP51600010485 | NEAR NEW ENGLISH SCHOOL, Nashik, 422003 | - | - | 31 Aug 2017 | Completed |
| CONSTRUCTION OF 49 TS MIGP51600013395 | Nashik, Nashik, 422003 | - | - | 4 Oct 2017 | Completed |
| Construction of 57LIG 17Shops 10 Offices at S No 517 520 521 523 Plot No P1 at Satpur NashikP51600027964 | Satpur Colony, Nashik, 422007 | - | - | 21 Jan 2021 | Registration lapsed |
What this promoter declares as its own experience
Nashik Housing And Area Development Board declares experience on 11 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| CONSTRUCTION OF 192 TS EWS 112 TS LIG 112 TS MIG | 24 Mar 2015 | 5 Aug 2015 | +4 months |
| CONSTRUCTION OF 192 TS EWS 112 TS LIG 112 TS MIG | 24 Mar 2015 | 15 Aug 2015 | +5 months |
| CONSTRUCTION OF 192 TS EWS 112TS LIG AND 112TS MIG | 24 Mar 2015 | 15 Aug 2015 | +5 months |
| Constuction of 35 MIG Ts and 12 Shops | 2 Sep 2015 | 2 Sep 2016 | +12 months |
| Construction of 216 TS EWS and 80 ts LIG at Shrirampur Ahmednagar | 30 Jun 2018 | 23 Mar 2018 | On time |
| CONSTRUCTION OF 216 TS EWS 80TS LIG AT SHRIRAMPUR AHMADNAGAR | 30 Jun 2018 | 23 Mar 2018 | On time |
| CONSTRUCTION OF 216 TS EWS 80 TS LIG AT SHRIRAMPUR AHMEDNAGAR | 30 Jun 2018 | 30 Jun 2018 | On time |
| Construction of 216ts EWS and 80ts LIG at Shrirampur Ahmednagar | 30 Jun 2018 | 30 Jun 2018 | On time |
| CONSTRUCTION OF 154 TS EWS I AND 24 TS EWS II TOTAL 178 TS ON S NO 36/B/1 AT KAMATHWADE NASHIK p51600019848 | 30 Dec 2023 | 31 Jan 2022 | On time |
| Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi Ahmednaga p52200019849 | 30 Dec 2023 | 18 Apr 2022 | On time |
| CONSTRUCTION OF 42 TS EWS UNDER PMAY p51600025949 | 30 Mar 2026 | 21 Nov 2023 | On time |
Frequently asked questions
How do I verify Nashik Housing And Area Development Board as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Nashik Housing And Area Development Board?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.