CIN U01210MH2007PTC174746 · Company · attribution by exact filing name, entity resolution in progress

Manjri Horse Breeders' Farm Private Limited has 6 registrations in this build, including Shapoorji Pallonji Treetopia Phase 1 and Shapoorji Pallonji Treetopia Phase 2. Its filings disclose 1 earlier MahaRERA project, none completed yet.

6Registrations in this build
1Past projects disclosed
no completions yetMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Shapoorji Pallonji Treetopia Phase 1Pune, Maharashtra1620%Registered
Shapoorji Pallonji Treetopia Phase 2Pune, Maharashtra1160%Registered
Shapoorji Pallonji Treetopia Phase 3Pune, Maharashtra840%Registered
Shapoorji Pallonji Treetopia Phase 4Pune, Maharashtra180%Registered
Shapoorji Pallonji Treetopia Phase 5Pune, Maharashtra180%Registered
Shapoorji Pallonji Treetopia Phase 6Pune, Maharashtra850%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Shapoorji Pallonji Treetopia Phase 1
PP1261012501803
30 Sep 2028Not completed yetOngoing

Frequently asked questions

How do I verify Manjri Horse Breeders' Farm Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U01210MH2007PTC174746 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Manjri Horse Breeders' Farm Private Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.