Home / Developers / KS GROUP OF COMPANIES
KS GROUP OF COMPANIES: RERA track record
GSTIN 27AAXFK9254H1ZJ · Partnership · attribution by exact filing name, entity resolution in progress
KS GROUP OF COMPANIES has 3 registrations on MahaRERA, including ZEN VRINDAVAN and zen 11. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time.
Projects by this developer
Showing all 3 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| MOHINI AKSHAYPR1180002500770 | DAHISAR EAST, Mumbai Suburban, 400068 | 57 | 0% | 15 Sep 2025 | Registered |
| zen 11P51800046012 | dahisar east, Mumbai Suburban, 400068 | - | - | 15 Jun 2022 | Registration lapsed |
| ZEN VRINDAVANP51800046080 | DAHISAR EAST, Mumbai Suburban, 400068 | - | - | 15 Jun 2022 | Registration lapsed |
What this promoter declares as its own experience
KS GROUP OF COMPANIES declares experience on 2 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 2 registrations MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| zen 11 P51800046012 | 31 Mar 2024 | 8 Jul 2024 | +3 months |
| ZEN VRINDAVAN P51800046080 | 31 Dec 2024 | 25 Oct 2024 | On time |
Frequently asked questions
How do I verify KS GROUP OF COMPANIES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAXFK9254H1ZJ on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with KS GROUP OF COMPANIES?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.