Krishnakumar Ramsinh Parmar: RERA track record

Individual ยท attribution by exact filing name, entity resolution in progress

Krishnakumar Ramsinh Parmar has 2 registrations in this build, including MANORATH RESIDENCY PHASE - 2 and MANORATH RESIDENCY PHASE-3. Its filings disclose 6 earlier MahaRERA projects: 3 of 6 past projects completed on time.

2Registrations in this build
6Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
MANORATH RESIDENCY PHASE - 2Dadra & Nagar Haveli, Maharashtra--Completed
MANORATH RESIDENCY PHASE-3Dadra & Nagar Haveli, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Row House No 5-9 , Manorath Residency
16 May 201214 May 2012On time
Landmark Prestige-A , F-Type Building
30 Sep 201222 Oct 2012+1 months
Row House 10-12 , Manorath Residency
10 Jan 20146 Sep 2013On time
KUBER , G1 Building, 4BHK , Manorath Residency
30 Dec 201424 Aug 2015+8 months
SHREE RAM - A Wing , Building E-Type A-Wing , Manorath Residency
30 Dec 20157 Mar 2017+14 months
MANORATH RESIDENCY PHASE-2
31 Dec 201931 Dec 2019On time

Frequently asked questions

How do I verify Krishnakumar Ramsinh Parmar as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Krishnakumar Ramsinh Parmar?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.