ReraGenieLog inGet a buyer report

Home / Developers / JAYASHREE VINOD PATKAR

JAYASHREE VINOD PATKAR: RERA track record

Individual ยท attribution by exact filing name, entity resolution in progress

JAYASHREE VINOD PATKAR has 4 registrations on MahaRERA, including SHEESH MALL and SAI ENCLAVE. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 4 past projects completed on time.

4RERA registrations
4Past projects disclosed
+1 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when JAYASHREE VINOD PATKAR registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 4 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
SAI ENCLAVEP52800019757NEAR ROTARY SCHOOL, Ratnagiri, 415709--5 Mar 2019Registration lapsed
SAI SYMPHONYP51600027626NEAR JAIPUR HOUSE, Nashik, 422005--25 Dec 2020Completed
SHEESH MALLP52800014520DAAK BUNGLOW, Ratnagiri, 415709--8 Dec 2017Registration lapsed
VIMAL ICON PHASE 2P51600031661MAKHMALABAD, Nashik, 422003--3 Nov 2021Registered

What this promoter declares as its own experience

JAYASHREE VINOD PATKAR declares experience on 4 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SAMARTH CONSUNTANTS
20 Mar 201319 Jun 2013+3 months
VIMAL HEIGHTS
13 Aug 201411 Jul 2014On time
SHEESH MALL
P52800014520
31 Mar 201923 Jan 2020+10 months
SAI SYMPHONY
P51600027626
30 Jun 202228 Dec 2021On time

Frequently asked questions

How do I verify JAYASHREE VINOD PATKAR as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with JAYASHREE VINOD PATKAR?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the JAYASHREE VINOD PATKAR developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.