Home / Developers / BMK PROPERTIES PRIVATE LIMITED
BMK PROPERTIES PRIVATE LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
BMK PROPERTIES PRIVATE LIMITED has 5 registrations in this build, including KAKADE RESIDENCY and KAKADE- SANJEEVANI. Its filings disclose 6 earlier MahaRERA projects: 5 of 6 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| KAKADE RESIDENCY | Pune, Maharashtra | - | - | Completed |
| KAKADE- SANJEEVANI | Pune, Maharashtra | - | - | Completed |
| Daulat Park-1 | Pune, Maharashtra | 18 | 0% | Registered |
| Daulat Park-2 | Pune, Maharashtra | 15 | 0% | Registered |
| 42 Park Street | Pune, Maharashtra | 59 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| DURVANKUR | 5 Nov 2012 | 5 Nov 2012 | On time |
| KAKADE HEIGHTS | 5 Nov 2013 | 5 Nov 2013 | On time |
| KAKADE SRUSHTI | 22 Dec 2014 | 22 Dec 2014 | On time |
| VRUNDAVAN | 26 Sep 2016 | 26 Sep 2016 | On time |
| KAKADE RESIDENCY P52100004336 | 31 Dec 2017 | 31 Dec 2017 | On time |
| KAKADE- SANJEEVANI P52100028898 | 30 Jun 2023 | 29 Jun 2024 | +12 months |
Frequently asked questions
How do I verify BMK PROPERTIES PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with BMK PROPERTIES PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.