Bhavya Infrastructures India Private Limited: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Bhavya Infrastructures India Private Limited has 2 registrations in this build, including Bhavya Heights and Bhavya Enclave. Its filings disclose 7 earlier MahaRERA projects: 1 of 7 past projects completed on time.

2Registrations in this build
7Past projects disclosed
+2 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Bhavya HeightsMumbai Suburban, Maharashtra--Registration lapsed
Bhavya EnclaveMumbai City, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Laxmi Palace
1 May 20041 Aug 2004+3 months
Bhavya CHS
1 Sep 20051 Nov 2005+2 months
Anand Villa
1 Jan 20061 Mar 2006+2 months
Bhavya Palace
1 Jul 20091 Sep 2009+2 months
Bhavya Plaza
1 Dec 20101 Feb 2011+2 months
Bhavya Renu CHS
1 Mar 20121 Mar 2012On time
Bhavya Sphurti CHS
1 Mar 20121 Apr 2012+1 months

Frequently asked questions

How do I verify Bhavya Infrastructures India Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Bhavya Infrastructures India Private Limited?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.