Akar Creations Private Limited: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Akar Creations Private Limited has 1 registration in this build, including Akar Pinnacle. Its filings disclose 9 earlier MahaRERA projects: 7 of 9 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Akar Pinnacle | Mumbai Suburban, Maharashtra | - | - | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Profit Centre | 30 Apr 2009 | 13 Apr 2009 | On time |
| Aquamarina Phase I | 31 Jul 2009 | 20 May 2009 | On time |
| Akar Green Empire | 31 Jul 2010 | 16 Jul 2010 | On time |
| Aquamarina Phase II | 31 Dec 2010 | 21 Sep 2010 | On time |
| Akar Excelsior Phase I | 31 Dec 2012 | 17 Oct 2012 | On time |
| Akar Habitat | 31 Jul 2013 | 29 Jul 2013 | On time |
| Akar Gardens | 31 Mar 2015 | 7 Apr 2015 | On time |
| Akar Harmony | 30 Apr 2015 | 11 Mar 2015 | On time |
| Akar Heights | 31 Aug 2015 | 1 Apr 2016 | +7 months |
Frequently asked questions
How do I verify Akar Creations Private Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Akar Creations Private Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.