AJIT GIRDHARILAL NAHAR: RERA track record

Individual ยท attribution by exact filing name, entity resolution in progress

AJIT GIRDHARILAL NAHAR has 5 registrations on MahaRERA, including GIRIPUSHP and Green City. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 6 past projects completed on time.

5RERA registrations
6Past projects disclosed
+1 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when AJIT GIRDHARILAL NAHAR registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 5 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Green City Phase II J BuildingPC1260002602123Shivane, Pune, 411023490%1 Oct 2026Registered
GIRIPUSHPP52100002063Pune (M Corp.), Pune, 411004--31 Jul 2017Completed
Green CityP52100002420Shivne (Part), Pune, 411023--1 Aug 2017Completed
GREEN CITY PHASE II K BUILDINGP52100026930SHIVANE, Pune, 411023--3 Nov 2020Registration lapsed
PeriwinkleP52100017310-, Pune, 412207--2 Aug 2018Completed

What this promoter declares as its own experience

AJIT GIRDHARILAL NAHAR declares experience on 6 earlier projects. 3 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

3 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 3 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Sujit Complex
30 Apr 200731 Jul 2007+3 months
New Ankita Residency
31 Aug 200830 Nov 2008+3 months
Sachita Apartment
31 Mar 201531 May 2015+2 months
Green City
P52100002420
30 Dec 202131 Dec 2020On time
Periwinkle
P52100017310
30 Dec 202430 Dec 2024On time
GREEN CITY PHASE II K BUILDING
P52100026930
30 Jun 202530 Jun 2025On time

Frequently asked questions

How do I verify AJIT GIRDHARILAL NAHAR as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with AJIT GIRDHARILAL NAHAR?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the AJIT GIRDHARILAL NAHAR developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.