Adarsh Vastu Nirmiti Pvt. Ltd.: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Adarsh Vastu Nirmiti Pvt. Ltd. has 5 registrations in this build, including ADARSH DEEP and ADARSH KRUTIKA. Its filings disclose 6 earlier MahaRERA projects: 0 of 6 past projects completed on time.

5Registrations in this build
6Past projects disclosed
+4 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
ADARSH DEEPSatara, Maharashtra--Registered
ADARSH KRUTIKASatara, Maharashtra--Registration lapsed
ADARSH ANURADHASatara, Maharashtra--Registration lapsed
ADARSH SURYA REVATISatara, Maharashtra--Registration lapsed
Adarsh UttaraSatara, Maharashtra--Registration lapsed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Adarsh Sangam
19 Feb 201129 Jul 2011+5 months
Adarsh Vishwa
15 Oct 201218 Feb 2013+4 months
Adarsh Shrushti
10 Dec 201216 Apr 2013+4 months
Adarsh Shivneri
25 Jan 201329 May 2013+4 months
Adarsh Gharkul
18 Oct 201317 Feb 2014+4 months
Adarsh Corner
12 Oct 201424 Feb 2015+4 months

Frequently asked questions

How do I verify Adarsh Vastu Nirmiti Pvt. Ltd. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Adarsh Vastu Nirmiti Pvt. Ltd.?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.