AADIRAJ BUILDERS AND DEVELOPERS: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
AADIRAJ BUILDERS AND DEVELOPERS has 1 registration in this build, including RAJNAKSHATRA. Its filings disclose 7 earlier MahaRERA projects: 5 of 7 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| RAJNAKSHATRA | Satara, Maharashtra | - | - | Registration lapsed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| MATOSHRI HIRAAI CHAVAN NAGAR | 30 Jun 2010 | 30 Mar 2017 | +81 months |
| HIRAAI GOLDEN CITY 3 | 30 Jun 2011 | 31 Mar 2011 | On time |
| Moraya Arcade | 31 Dec 2012 | 27 Feb 2013 | +2 months |
| MORAYA COMPLEX | 17 Jun 2013 | 29 May 2013 | On time |
| HIRAAI GOLDEN CITY 1 | 31 Mar 2014 | 31 Jan 2014 | On time |
| HIRAAI GOLDEN CITY 2 | 30 Jun 2014 | 31 Mar 2014 | On time |
| MORAYA PRESTIGE | 30 Apr 2015 | 30 Mar 2015 | On time |
Frequently asked questions
How do I verify AADIRAJ BUILDERS AND DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with AADIRAJ BUILDERS AND DEVELOPERS?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.