New projects and RERA data in Morbi district, Gujarat
9 projects are registered in Morbi district: 1,259 units across them, 2 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 9 covered registrations, 1 have revised their promised completion date. The median project here is 12% booked as of the current data. Every figure comes from the projects' own GujRERA filings.
Projects in Morbi
Showing all 9 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| FLORA AKSHAR CITY | FLORENTINA REALTY LLP | 324 | 25% | 6 Oct 2021 | Valid until 31 Dec 2025 |
| Swagat ArcadeVajepar, 363642 | Swagat Developers | 226 | 0% | 24 Dec 2025 | Valid until 30 Sep 2026 |
| 192 EWS I & 22 SHOPS AT HASANPAR WANKANERHasanpar, 363621 | GUJARAT HOUSING BOARD | 214 | 88% | 25 Feb 2019 | Valid until 30 Jun 2021 |
| FLORA PALMS | FLORENTINA REALTY LLP | 184 | 73% | 4 Feb 2022 | Valid until 31 Dec 2026 |
| SUNFLORA HEIGHTSVajepar, 363641 | SUNFLORA REAL ESTATE LLP | 102 | 12% | 25 Apr 2019 | Valid until 30 Jun 2023 |
| EDEN ARCADEMADHAPAR, 363641 | DURLABHJI LALJI RANGPARIA Propritorship of EDEN Arcade | 82 | 0% | 1 Oct 2026 | Valid until 30 Nov 2026 |
| Sahajanand TownshipMorbi | Pramukh Builders | 56 | 0% | 17 Oct 2019 | Valid until 30 Sep 2021 |
| YOGI PLAZAMorbi, 363641 | YOGI DEVELOPERS | 41 | 37% | 7 Aug 2019 | Valid until 30 Dec 2022 |
| VRUJ RESIDENCYWankaner | VRUJ RESIDENCY | 30 | 0% | 20 Jun 2020 | Valid until 30 Mar 2025 |
Developers active in Morbi
FLORENTINA REALTY LLP (2), Swagat Developers (1), GUJARAT HOUSING BOARD (1), SUNFLORA REAL ESTATE LLP (1), DURLABHJI LALJI RANGPARIA Propritorship of EDEN Arcade (1), Pramukh Builders (1). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Morbi projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 12% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Morbi project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Morbi project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.
Report an errorShare feedbackData from official GujRERA filings.