Stalled project acquisition starts with a row like this one: a lapsed registration in Pune district, two towers, 180 flats, 126 of them filed as booked, the construction checklist at 62 percent. Finishing it might cost Rs 46 crore, the buyers who booked might still owe Rs 30 crore, and 54 unsold flats are the margin. Bought on the right terms, it is a project with its permissions in place and most of its customers already signed. Bought on the wrong ones, it is every promise the last promoter missed, now owed by you. The figures in that example are illustrative; the supply is not. As updated on 11 October 2026, 13,832 of the 56,194 published MahaRERA registrations read Registration lapsed.

Key takeaways

  • As updated on 11 October 2026, 13,832 of 56,194 published MahaRERA registrations read Registration lapsed; 2,961 of them file unit counts, and 1,344 of those are at least half booked, holding 1,04,442 booked units.
  • A lapse is a filing status, not proof that work stopped: of the 5,324 lapsed projects whose promoters answered MahaRERA's notices by January 2025, 3,517 submitted occupancy certificates.
  • There are three routes in: a negotiated takeover that revives the registration under section 7(3) and transfers it under section 15, finishing the works for the allottees after MahaRERA acts under section 8, or a resolution plan in an insolvency before the NCLT.
  • Section 8 lets MahaRERA have the remaining works done by the association of allottees or in any other manner after a lapse or a revocation, and gives the association the first right of refusal only where the registration was revoked.
  • Last-mile money is thinner than the headlines: the first SWAMIH fund had committed its whole corpus by 5 December 2025, and we found no report of the Rs 15,000 crore second fund's first investment by October 2026.

Anita reads the lapsed list as a pipeline

Anita Rao (our illustrative BD head at a mid-size developer scouting MMR and Pune micro-markets) has a new brief: after one change-of-promoter file for an Active project, her firm wants her to read the lapsed list as a source of projects to finish and sell. She sorts by booked share and construction progress, then reads each survivor's complaints, litigation and declared charges before anyone calls a promoter. Her firm bids at the number that survives a four-quarter slippage stress, so every candidate is priced from a date she believes, not the date on the filing.

Three ways in, each at its strongest

A lapsed project can change hands three ways, and the register usually says which of them are open.

Through the promoter. Where the promoter is solvent and willing, the deal is bilateral, and two approvals carry it. Section 7(3) of the RERA Act lets the Authority, instead of revoking a registration, keep it in force on further terms and conditions, and MahaRERA uses it for extensions beyond the one year section 6 allows. Since Order No. 07/2019 it has asked for the consent of at least 51 percent of allottees; Order No. 40/2022 of 27 December 2022 lets a promoter apply with the consents it has and its reasons for the rest. Then the change of promoter: section 15 needs the written consent of two-thirds of the allottees and MahaRERA's approval, and the incoming promoter takes on the pending obligations to buyers, the file the RERA project transfer guide walks through. Its strongest case is control: the land, permissions and agreements stay where they are, and the price is a negotiation between two parties who both want out.

Through the allottees. Section 8 applies on a lapse or a revocation. The Authority may consult the appropriate Government and have the remaining works carried out by the competent authority, by the association of allottees or in any other manner it decides; no such direction takes effect until the period for appeal has expired; and where the registration was revoked, the association has the first right of refusal. Revocation comes from section 7: a default under the Act, rules or regulations, a breach of the approvals or unfair practice, after at least 30 days' notice. A developer enters this route as the allottees' choice of contractor or partner, not as the promoter's buyer. In an order on a nine-building township near Taloja, MahaRERA revoked the registration and allowed the homebuyers' association and the housing society to finish the work themselves or bring in a new developer, as The Realty Today reported. The strongest case: the negotiation is with the people who want the building, not with the promoter who did not finish it.

Through the NCLT. Where the promoter is a company in insolvency, the project moves with the corporate insolvency resolution process. Since the 2018 amendment to the Insolvency and Bankruptcy Code, money raised from allottees is financial debt, which the Supreme Court upheld in Pioneer Urban in 2019. Since February 2024 a resolution professional may, with the creditors' committee's approval, invite a resolution plan for each real estate project or group of projects, so an acquirer can bid for the tower it wants rather than the whole company. The IBBI's February 2025 amendment let the resolution professional hand possession to allottees who have paid, with 66 percent of the committee's votes, and let the committee relax eligibility, performance security and deposit conditions for allottee associations bidding as resolution applicants. The buyers are therefore voters and possible rival bidders at once. The strongest case: the claims against the company are collected and voted on in one process instead of negotiated one by one. When the borrower fails sets out how long that queue has run.

Where the money comes from. Every route ends at the same question: who pays for the rest of the building? The government's answer has been SWAMIH, a last-mile fund sponsored by the Ministry of Finance and managed by SBICAP Ventures, which lends to RERA-registered projects stalled for want of money, in the affordable and mid-income segment with units up to 200 square metres, and net-worth positive. By 15 December 2025 it had delivered about 61,000 homes across 110 projects, according to government data reported by IANS and Business Today in January 2026, and it had committed its whole investible corpus before its investment period ended on 5 December 2025, PTI reported that month. The Union Budget of 1 February 2025 announced a second fund of Rs 15,000 crore to complete another 1 lakh homes. In Parliament in March 2026 the Finance Minister described the government as in the process of launching it, and we found no report of its first investment by October 2026. Price a takeover on lenders who are lending this year.

The three routes side by side

QuestionThrough the promoterThrough the allotteesThrough the NCLT
Legal gateSection 7(3) revival, then a section 15 transferA section 8 direction after a lapse or a section 7 revocationA resolution plan under the IBC, approved by the creditors and the tribunal
Who you negotiate withThe promoter, its lender and the landownersThe association of allottees, under MahaRERA's directionThe resolution professional and the committee of creditors
Consent you need51 percent of allottees for the revival, or reasons why not; two-thirds for the transferThe association's choice of you, and MahaRERA's orderThe committee's vote, where allottees sit as financial creditors
What you inheritEvery pending obligation to the buyersThe works, the buyers and the terms the order setsWhat the approved plan says, project by project where the plan is project-wise
The main riskPaying the promoter before MahaRERA approvesAn appeal against the directionTime, and rival bids, the allottees' included
Where the money comes fromYour equity, your lender, the project's receivablesThe buyers' balances, your lender, a last-mile fundThe plan's own means of finance

What the lapsed list holds

The 13,832 lapsed registrations are mostly old: 4,285 were registered in 2017, between 1,125 and 1,738 in each year from 2018 to 2023, 302 in 2024 and 40 in 2025. Only 2,961 file unit counts, the first filter an acquirer meets: a project that does not file its sales cannot be priced from the register.

Lapsed MahaRERA registrations by the share of their units filed as booked(registrations, of the 2,961 lapsed registrations that file unit counts)
None booked712
1 to 25 percent347
26 to 50 percent605
51 to 75 percent510
76 to 100 percent787

Source: ReraGenie analysis of 13,832 Registration lapsed projects among 56,194 published MahaRERA registrations, as updated on 11 October 2026

1,344 lapsed registrations are at least half booked, and they hold 1,04,442 booked units of their 1,28,898. They have customers to serve, money still due and the most signatures to collect. The 712 filing nothing booked are closer to land and permissions than to a rescue, though a filing of zero never proves no flat was sold. Where the lapsed projects are maps the same list by district; read it for the catchment and these buckets for the project.

Lapsed MahaRERA registrations by the mean of their filed construction checklist(registrations, of 13,832 Registration lapsed)
Up to 25 percent3,251
26 to 50 percent2,761
51 to 75 percent2,554
76 to 99 percent3,742
100 percent704
Not filed820

Source: ReraGenie analysis, as updated on 11 October 2026. Checklist mean is the promoter's own filing, each activity capped at 100 percent.

3,742 lapsed registrations file a checklist between 76 and 99 percent, and 704 file 100. Projects that far along are where a lapse is most likely to be paperwork rather than a stall, and MahaRERA's own drive found plenty of paperwork. It served notices on 10,773 lapsed projects from December 2024; by January 2025 promoters of 5,324 had answered, 3,517 of them with occupancy certificates and 524 asking for more time, and it had suspended the registrations of more than 1,950 projects and frozen their accounts, according to its statement reported by Punekar News and Moneylife that month. Two more counts frame the diligence: 1,751 lapsed registrations answer the charge question and 196 of them declare a charge, and 2,352 carry at least one complaint, 17.0 percent against 11.0 percent of Active registrations.

Warning

A lapse is not proof the project stopped. The status means the last filed completion date passed without a completion or extension filing, and some lapsed projects are finished on the ground and never filed Form 4. Before pricing a rescue, visit the site and ask the planning authority whether an occupancy certificate was issued. A finished building with missing paperwork is a compliance problem for its promoter, not a takeover for you.

An analogy: a factory with orders on the books

A lapsed registration is a factory whose operating licence has expired with customer orders open and advances already banked. You can buy it from the owner and apply to renew the licence. You can be engaged by the customers who paid in advance, with the regulator's blessing, to finish their orders. Or you can bid in the creditors' sale. The machinery is the same in all three; what changes is who signs, who votes and which liabilities come with the keys.

Six questions that decide it

  1. Is it stalled, or only unfiled? Read the construction progress by building and the occupancy certificate slot before the promoter's account. The district pace benchmarks show what a checklist that is still moving looks like.
  2. Who owns the land, and who holds a charge on it? The filing names the landowners and, where the question is answered, the lender and the amount. A mortgage on the land survives the registration's lapse, and an unanswered filing never means the land is free. Who holds the charge shows what the register declares about lenders; run your own title search as well.
  3. Can the promoter still sign? A promoter company in insolvency is not your counterparty any more; the process is. Its litigation disclosure and the case numbers on the project page usually say so first.
  4. Is there a majority to be had? 51 percent for a revival and two-thirds for a transfer, counted against the allottee list, not the forms collected.
  5. Does the money still due cover the cost to finish? Receivables and unsold stock against the cost to complete, on your schedule, not the filing's. If the gap is negative, no route fixes it; only the price can.
  6. Whose last-mile money is available today? The first SWAMIH fund is committed and the second had not reported an investment. Any other lender will read the same register you did, as five filing signals describes.

The snag in Anita's file

Anita's shortlist came down to the Pune-district row in the opening: a 2019 registration, two towers, 180 flats, 126 filed as booked, the checklist at 62 percent, a charge declared to a co-operative bank and nine complaints, three of them already heard. The promoter was willing to sell. The snag was in the litigation disclosure: an operational creditor's insolvency petition against the promoter company was pending before the NCLT, not yet admitted. A bilateral deal could be overtaken by an admission, and money paid to the promoter in the meantime would sit in a company someone else might soon be running.

Her firm priced two bids instead of one: a section 15 offer conditional on the petition being withdrawn, and a project-wise resolution plan if it was admitted, each stressed for a four-quarter slip from the firm's own schedule. Which bid went in is not part of this story. Names and numbers in this story are illustrative.

The petition was on the project's free page all along, under litigation with its case number. Every MahaRERA registration has such a page on reragenie.com, free to read: go through the complaints, litigation and declared charges of each project on your shortlist before calling its promoter.

What the project analysis answers

ReraGenie's Rs 2,999 project analysis assembles the questions the free page leaves open, for one project:

  • The promoter's record: its registrations and how they ended, a concurrency timeline, and its complaints, litigation and appeals.
  • Whether the unsold flats can sell: the registered projects within 2 km and 5 km with their supply, and an absorption cross-section of sold share against project age, many projects photographed on one day and never a sales history.
  • The date you would be pricing: the district's distribution of possession slip with the project's position and the count stated, and the possession landing schedule with an overdue bucket.

For a pincode with at least 20 registered projects, the Rs 2,999 area report tables up to 25 of its active registrations, largest first, with progress and bookings per month where both are filed.

Methodology and sources

  • ReraGenie analysis of 56,194 published MahaRERA registrations, 13,832 of them Registration lapsed, as updated on 11 October 2026; booked share over the 2,961 filing unit counts, checklist mean with each activity capped at 100 percent. A lapse is never a verdict on the promoter.
  • RERA Act, 2016, sections 6, 7, 8 and 15; MahaRERA Orders No. 07/2019, 40/2022 and 40A/2023, as summarised by Mondaq; section 15 as summarised by the Free Press Journal, September 2025; the Taloja order as reported by The Realty Today.
  • MahaRERA's lapsed-project notices: its statement of 9 January 2025, reported by Punekar News and Moneylife.
  • IBC section 5(8)(f); Pioneer Urban (2019); IBBI amendments of February 2024 (Business Standard) and 3 February 2025 (IBBI, LiveLaw); IBBI discussion paper of 30 June 2026.
  • SWAMIH: eligibility as summarised by ClearTax; deliveries from government data reported by IANS and Business Today, January 2026; corpus commitment, PTI, December 2025; the second fund from the Union Budget of 1 February 2025 and the Finance Minister's statement in Parliament, March 2026.

This article is educational and not legal advice. Confirm the position for your project with your advocate and the authority concerned.