One MahaRERA project in three that has moved its completion date by 25 months or more carries at least one complaint. Among projects that never moved the date, it is fewer than one in eleven. As updated on 11 October 2026, 1,663 of the 4,970 published projects with a slip of 25 months or more (33.5 percent) carry a complaint, against 3,853 of the 43,244 with no slip (8.9 percent). For a promoter trying to reduce RERA complaints, that is the first thing the register says: buyers complain about time. The second is that the climb starts early, within months of the first promised date, long before a project looks troubled to anyone inside it.
Key takeaways
- As updated on 11 October 2026, 7,167 of the 56,194 published MahaRERA projects (12.8 percent) carry at least one complaint, 36,858 complaints in all.
- The share with a complaint rises with every band of possession slip: 8.9 percent with no slip, 13.6 percent at 1 to 6 months, 20.2 percent at 7 to 12, 24.4 percent at 13 to 24 and 33.5 percent at 25 months or more.
- 24.7 percent of projects that have taken at least one extension carry a complaint, against 8.8 percent of those that have not; lapsed registrations carry one at 17.0 percent.
- MahaRERA disposed of 6,945 complaints in 2025, up from 3,824 in 2024, while 5,039 new complaints were filed, up from 3,880.
- A realistic first date, an early extension with its reason, telling allottees before the register does and offering conciliation all come before a complaint, and none of them reduces what a buyer is owed under section 18.
The question this data answers
Why do buyers complain, and what in a promoter's own conduct moves the odds? The answer matters beyond the hearing. A complaint is public: it sits on the register against the project, where the next buyer, lender and landowner read it. It travels into any further extension, because MahaRERA's Order No. 40A/2023 asks a promoter seeking one to list the complaints and the orders passed. And a delay complaint usually ends in interest: section 18 of the RERA Act entitles an allottee who stays in the project to interest for every month of delay until possession, at SBI's highest MCLR plus 2 percent in Maharashtra, 10.90 percent on the 8.90 percent MCLR of June 2026.
How many projects carry a complaint
Source: ReraGenie analysis of 56,194 published MahaRERA projects, as updated on 11 October 2026. A complaint count is not a finding against the promoter.
Complaints cluster. The 7,167 projects carry about five each on average, and the register holds a further 6,997 filed as miscellaneous non-compliance complaints. Read every figure here with one caveat: a complaint is not a finding against the promoter. Many are pending, withdrawn or settled, and some concern matters other than delay.
Complaints rise with every band of slip
Source: ReraGenie analysis of the 56,187 published MahaRERA projects filing both a first and a current promised completion date, as updated on 11 October 2026
A slip of one to six months already lifts the share by half, from 8.9 to 13.6 percent. Seven to twelve months more than doubles the no-slip figure, and past two years it is nearly four times as high. Two cautions travel with the curve. It shows complaints rising with slip, not that slip caused each complaint. And "no slip" includes projects whose date has not yet arrived, which flatters the baseline, because a project cannot be late before its date.
Extensions: the slip made public
Source: ReraGenie analysis of 56,194 published MahaRERA projects, as updated on 11 October 2026
An extension is the moment a slip becomes a public filing, and projects carrying one are almost three times as likely to carry a complaint. That is not an argument against extending. The alternative is worse company: 2,352 of the 13,832 Registration lapsed projects (17.0 percent) carry a complaint, against 2,200 of 20,089 Active ones (11.0 percent), and developers reading the lapsed list for takeovers price those complaints as liabilities they inherit. Completion does not end the conversation either: 2,569 of 21,686 Completed projects (11.8 percent) carry one.
What an extension does not do is move the buyer's date. It changes the registration, not the agreement for sale, and as an expert told the Free Press Journal's Consumer Connect column, a MahaRERA extension does not deprive homebuyers of claiming delay interest. Your own project's free page on reragenie.com lists its complaints with case numbers and its extensions with the reason you gave: read it the way your next buyer will, before a complaint is the first thing on it.
The forum is faster than it was
MahaRERA disposed of 6,945 complaints in 2025, up from 3,824 in 2024, while 5,039 new complaints were filed, up from 3,880, according to the figures it released in January 2026, as reported by The Realty Today and Outlook Money. With disposals outrunning new filings, a complaint reaches a hearing sooner than it did, which shortens the time a promoter has to answer the buyer outside one.
The other door is conciliation. Section 32(g) of the Act asks the Authority to recommend measures to facilitate amicable conciliation of disputes between promoters and allottees through forums set up by consumer or promoter associations, and MahaRERA's benches pair a member from a developers' organisation with one from a consumer organisation. In December 2023, MahaRERA reported 1,343 complaints resolved through 52 conciliation forums, with 876 then in hearing, as Punekar News reported that month.
An analogy: the delivery date
A supplier who will miss a delivery date chooses when the customer finds out. Told in week one that the order will be three weeks late, with a reason and a new date, most customers reschedule. Finding out on the due date, from an empty loading bay, they escalate. The delay is identical; the notice is not. For a project, the register is the loading bay: a buyer who learns of a slip from a revised date on the portal has been told by the regulator, not by the promoter.
Iqbal's eight months
Iqbal (our illustrative Thane builder) keeps a dashboard of QPR deadlines and his competitors' compliance flags, and since reading these figures he has added a line for his own projects' complaints against the slip bands above. His oldest active project is the one he extended once, by eight months, filing early with the approval correspondence attached. Before he filed, he wrote to every allottee: the reason, the revised stage-wise schedule for each wing, and a sentence saying the extension did not change the date in their agreement or their right to interest under it. He offered a meeting at the site office to anyone who wanted one.
Two buyers filed complaints anyway, both asking for delay interest, which was theirs to ask for. His reply to each set out the interest computed on the agreement's terms and offered the conciliation forum for any amount in dispute. One settled there; the other complaint is still to be heard. Names and numbers in this story are illustrative.
What a promoter can do before a complaint
- File a date you can keep. The first promised date is the baseline every buyer and every chart here measures from, and the curve rises within months of it. The district pace benchmarks show the progress a realistic date has to assume.
- Extend early, and say why. An extension filed before the date passes keeps the registration alive; one that is not becomes a lapse. For an extension beyond the first year MahaRERA asks for the consent of at least 51 percent of allottees, or, under Order No. 40/2022, the promoter's reasons where it could not be had. Ask with the reason and the new schedule in hand; extensions under MahaRERA covers the file.
- Tell allottees before the register does. Section 19(2) entitles an allottee to know the stage-wise time schedule of completion, including water, sanitation and electricity. A letter that mirrors each quarterly progress report, building by building, answers that right before anyone asks; the compliance calendar sets when those reports fall due.
- Pay what the agreement already owes. Delay interest under section 18 is the buyer's whether or not a complaint is filed. A promoter who computes and offers it, on the agreement's terms, removes the reason for that complaint.
- Offer conciliation, never in place of the complaint. The forum is a door both sides choose; the conciliation forum explains it from the buyer's side.
- Watch your own page as a buyer does. Competitors' QPRs are one half of Iqbal's dashboard; your own complaints and extensions, read against the bands above, are the other.
Nothing in this list narrows a buyer's rights. An extension moves the registration's date, not the agreement's; a quarterly letter is not a waiver; and conciliation is a door the buyer may choose, not one the promoter may close. A settlement that asks an allottee to give up a claim should say so in plain words.
What the project analysis shows about your own project
ReraGenie's Rs 2,999 project analysis, run on your own registration, reads it as a buyer, lender or landowner will:
- Where your date sits: the district's distribution of possession slip, with your project's position in it and the count stated, which places you on the curve above.
- Your record as filed: your registrations and how they ended, a concurrency timeline, and the complaints, litigation and appeals on them.
- The competition for a buyer's patience: the possession landing schedule nearby, with an overdue bucket.
Methodology and sources
- ReraGenie analysis of 56,194 published MahaRERA projects, as updated on 11 October 2026: 36,858 complaints, plus 6,997 miscellaneous non-compliance complaints; slip in whole months between the first promised and current completion dates, over the 56,187 projects filing both; extensions and status as filed. A complaint count is not a finding against a promoter, the figures show complaints rising with slip rather than slip causing each one, and "no slip" includes projects whose date has not yet arrived.
- MahaRERA's complaint figures for 2024 and 2025, released January 2026, as reported by The Realty Today and Outlook Money. Conciliation forums: MahaRERA's December 2023 figures, reported by Punekar News.
- RERA Act, 2016, sections 6, 7(3), 18, 19(2) and 32(g); Maharashtra RERA Rules, rule 18; MahaRERA Orders No. 07/2019, 40/2022 and 40A/2023, as summarised by Mondaq; the Free Press Journal's Consumer Connect column on extensions and delay interest. The 8.90 percent MCLR is the June 2026 figure this site uses; interest arithmetic is illustrative.
This article is educational and not legal advice. Confirm the position for your project with your advocate and the authority concerned.