Of the 9,641 Active MahaRERA projects registered since 2024 that file unit counts, 4,217 file not one unit as booked or sold. That is 43.7 percent, as updated on 11 October 2026, and it is why the median project in this cohort books 0.12 units a month. The construction progress benchmark is less startling: the median project fills its filed construction checklist at 1.36 percentage points a month. Both figures come from the filing as it stands today, not from a history. MahaRERA keeps only each project's current filing, so each pace here is where a project stands now, divided by how long it has been registered.
Key takeaways
- As updated on 11 October 2026, the 10,485 Active MahaRERA projects registered since 2024 that file the construction checklist have a median progress of 1.36 percentage points of the checklist a month.
- District medians run from 0.63 points a month in Mumbai City (194 projects) to 1.99 in Nashik (618); Pune's is 1.23 (2,750 projects) and Thane's 1.19 (1,699).
- 4,217 of the 9,641 cohort projects that file unit counts (43.7 percent) file zero units booked or sold, so the statewide bookings median is 0.12 units a month and four district medians read 0.00.
- Measured as a share of each project's units, the median booking pace is 0.28 percentage points a month, and 1.18 among projects filing at least one booking.
- Every figure is computed from the promoter's current filing, not a history, and a median describes the cohort: it is never a target or a verdict on any project.
The question this answers
A developer is asked whether a project is on pace by three readers at least: the lender comparing progress with money drawn, the landowner in a joint development watching the share it is owed, and the buyer comparing a shortlist. A pace needs a yardstick, and the register can supply one if it is built carefully.
The cohort here is the one ReraGenie's buyer report and comparison matrix benchmark against: registrations that are Active and were registered in 2024 or later, 11,096 of them. Two measures:
- Progress per month is the mean of the filed construction checklist, with each activity capped at 100 percent so that an impossible entry cannot lift the average, divided by the whole months since registration. The unit is percentage points of the checklist a month.
- Bookings per month is the units filed as booked or sold, divided by the same months, in units a month.
A district median is stated only where at least 20 projects file the measure.
Progress per month, by district
Source: ReraGenie analysis of 11,096 Active MahaRERA registrations made in 2024 or later, as updated on 11 October 2026. Mean of the filed checklist, each activity capped at 100 percent, over whole months since registration. Computed from the current filing, not a history.
The three largest districts in the cohort, Pune, Thane and Mumbai Suburban, hold 6,102 of the projects filing the checklist, and all three sit below the statewide median. The higher medians belong to smaller markets: Nashik, Kolhapur and Satara. The register does not say why, and these medians do not control for project size, height or type, which is the first thing to check before reading anything into a gap. Mumbai City, at 0.63, sits well below every other district shown.
As arithmetic only, 1.36 points a month is about 16 points of the checklist a year. That is not a forecast for any project, because work does not move evenly: the checklist can sit still through excavation and approvals and then move several activities in a quarter.
Bookings per month, by district
Source: ReraGenie analysis of 11,096 Active MahaRERA registrations made in 2024 or later, as updated on 11 October 2026. Units filed as booked or sold over whole months since registration. A filed zero never proves no flat was sold.
Two readings matter. First, the checklist and the bookings are separate facts: Nashik has the fastest progress median of any district shown and one of the slowest booking medians, 0.06 units a month. Second, the two medians in a district need not describe the same projects. Nagpur is the clearest case, with 629 projects filing unit counts and only 311 filing the checklist, so its two figures come from different sets. A median of 0.00 means at least half of that district's cohort files no booking at all.
Four in ten file no booking
Source: ReraGenie analysis, as updated on 11 October 2026. A filed zero is what the promoter last entered, not proof that no flat was sold.
This is what pulls the bookings medians so low, and it is a fact about filings before it is a fact about sales. A project that files bookings late reads as slow, and a zero in a filing never proves that no flat was sold.
Units a month also favours big projects: a 300-flat tower and a 20-flat building are not the same business. Measured as a share of each project's own units, the median across the 9,641 is 0.28 percentage points a month. Among the projects that file at least one booking it is 1.18, which is the fairer yardstick for any project that has started selling.
Before you quote a district median to a board, a lender or a landowner, check that your own last filing carries every booking and every activity it should, and that you are comparing the same measure: units with units, or share with share. A project is benchmarked on what it filed, not on what its sales office knows.
Outside the register: the market the cohort sells into
City counts from the consultancies set the background, and they do not always agree with each other. ANAROCK put July to September 2026 sales at about 31,750 homes in the Mumbai Metropolitan Region, up 5 percent on a year earlier, and 15,690 in Pune, down 6 percent; across the top seven cities, launches of about 1,14,320 units outran sales of about 1,00,220, and unsold stock rose 12 percent to about 6,30,590 units. PropEquity, counting differently, put Pune's sales for the same quarter down 16 percent to 17,860 units. A city count says how many homes sold. The register says which projects filed them, and how each is moving against its own age, which is what a benchmark needs.
An analogy: debtor days against the industry median
A finance team benchmarks its debtor days against the industry median. A firm collecting in 90 days where the median is 60 is not therefore badly run; it may sell to customers who pay slowly, and it should know why. The median tells it where to look, not what to conclude. These pace medians work the same way. A project below its district's median has a question to answer, often with a good answer, such as a podium-heavy design or a wing still waiting for its approvals. A project above it has not proved anything either.
Anita Rao places her firm's Pune tower
Anita Rao (our illustrative BD head) ran the numbers on her own firm's Pune tower, the one whose loan was classified as commercial real estate until its retail share was trimmed to about 8 percent of FSI. It registered 28 whole months before 11 October 2026 and files 240 flats. Its checklist mean stood at 41 percent, so its pace reads 1.46 points a month, against Pune's median of 1.23 across 2,750 projects. Names and numbers in this story are illustrative.
Bookings were the snag. In units the tower read 4.2 a month against a district median of 0.11, a comparison that says nothing, because the median project is far smaller. She switched to the share: 118 of 240 flats filed as booked over 28 months is about 1.76 points of its units a month, against 1.18 for cohort projects filing any booking at all. Then she found the filing was behind the sales office. The last quarterly filing carried 118 bookings when the sales team's count was 131, because agreements signed in the quarter's last weeks had not been entered, so on the register the tower read slower than it was. The next filing carried the full count, and her note to the board compared the tower with its district on the same footing a lender or a buyer reading the page would use.
What this means for a developer
- Compare like with like. Benchmark within the district and against projects of similar size, and say which measure you used. For bookings, use the share of units, not units.
- File on time and in full. Late or partial entries make a project read slower than it is, in front of every reader at once. The MahaRERA compliance calendar sets out the dates.
- Know where you sit before a lender asks. A lender's file reads progress against drawdown, as construction finance after the 2025 rules explains, and a pace below the district median is easier to explain early than an extension is later.
- Use the same yardstick on competitors. Your competitor's QPRs read individual rivals, and reading a micro-market from filings turns the same filings on a whole catchment.
Before you set your own projects against these medians, see how the register shows them: every free project page on reragenie.com carries construction progress by building and the possession timeline, first promised date against the current one, exactly as a lender or buyer sees them.
What the reports show for one pincode or one site
The Rs 2,999 area report covers one pincode with at least 20 registered projects, from the filings: the pincode's registrations, their status and possession slip, and a table of its active registrations with progress and bookings per month wherever both inputs are filed. The Rs 2,999 project analysis, run on one project or parcel location, adds an absorption cross-section, sold share against project age on one day, and the possession landing schedule with an overdue bucket. Neither is a history; both read the filing as it stands. For a parcel not yet bought, the order is the title search first and the market read second.
Methodology and sources
- Cohort: ReraGenie analysis of Active MahaRERA registrations made in 2024 or later, 11,096 of them, as updated on 11 October 2026. Progress per month is the mean of the filed construction checklist, each activity capped at 100 percent, over whole months since registration; 10,485 projects file it. Bookings per month is units filed as booked or sold over the same months; 9,641 projects file unit counts, 4,217 of them zero. District medians are shown only where at least 20 projects file the measure. Districts as filed: Raigarh is MahaRERA's spelling of Raigad, and Aurangabad the register's spelling of Chhatrapati Sambhajinagar.
- Caveats: the pace is computed from the current filing, not from a history, since MahaRERA keeps only the current filing; the checklist percentage is the promoter's own entry; a project that files bookings late reads as slow; a filed zero never proves no flat was sold; a median describes the cohort and is never a target or a verdict on any project.
- ANAROCK residential data for July to September 2026, as reported by Business Today on 29 September 2026; PropEquity data for July to September 2026, released on 26 September 2026 and reported by Trak.in.
Evaluating a micro-market or a land parcel?
The ReraGenie project analysis reads the filings around your parcel: supply, absorption and promoter records. Rs 2,999 per project; the area market report is a flat Rs 2,999 per pincode.
See the project analysis