In January 2025 MahaRERA froze the bank accounts and suspended the registrations of more than 1,950 projects whose promoters had not answered its notices on lapsed registrations, Moneylife reported that month; the notices had gone to about 10,773 projects in a drive that began in December 2024. A developer weighing a rera project transfer is buying exactly that kind of record. The registration, its dates, its accounts, its charges and its complaints all come with the project. Section 15 of the RERA Act sets the gate, and the incoming promoter answers for every promise the outgoing one made, on the original dates, so the work starts with reading what you are about to inherit.

Key takeaways

  • Section 15 of the RERA Act bars a promoter from transferring its majority rights and liabilities in a project without the prior written consent of two-thirds of the allottees, excluding the promoter, and the prior written approval of the Authority.
  • The incoming promoter must independently meet every pending obligation of the outgoing one, under the Act and under each agreement for sale, and the transfer gives it no extra time to complete.
  • MahaRERA's Circular No. 24/A of 23 July 2021, which superseded the 2017 procedure, has the incoming promoter file its own documents and a declaration and upload a registered undertaking to honour the existing agreements.
  • Changes in the promoter's internal shareholding that leave its obligations to buyers untouched generally need no consent; a voluntary merger of a promoter company holding registered projects is treated as a transfer.
  • As updated on 11 October 2026, 13,832 of the 56,194 published MahaRERA registrations read Registration lapsed, so the target's status is the first line of diligence, not the last.

What you need before you start

  • The target's registration number, its free page on ReraGenie's project pages and its page on the MahaRERA portal.
  • The seller's allottee ledger: every flat sold, every co-allottee named, every cancellation dated.
  • One copy of each version of the agreement for sale and allotment letter the seller has used.
  • The lender position: the sanction letter, a statement of dues, and the lender's view on a change of promoter.
  • The latest Forms 1, 2 and 3, the latest quarterly progress report and any extension orders.
  • Your own completion schedule for the remaining work, priced before anyone talks about consents.

The steps

Step 1. Read the registration before the seller's deck

Action. Pull the status, the first and current promised completion dates, every extension with the reason the promoter gave, complaints and litigation with case numbers, the declared charges and the seller's other registrations.

What you will see. As updated on 11 October 2026, the 56,194 published registrations read Completed 21,686, Active (MahaRERA's "Registered") 20,089, Registration lapsed 13,832, De-registered 499 and Revoked 81. On charges, 17,664 projects answer the question and 2,677 of them (15.2 percent) declare one; an unanswered filing never means the land is free of charges.

Red flag. A lapsed registration, accounts caught in a regulator's freeze, complaints already heard, or a charge declared to a lender nobody has mentioned. Each of these transfers to you with the project.

Step 2. Decide whether section 15 applies to your structure

Action. Write down how the deal will actually happen: the project assigned to your company, the seller's company bought, a merger, or a lender enforcing its security and handing the project on.

What you will see. MahaRERA's directions on section 15 (Circular No. 11/2017 of 8 November 2017, a circular of 4 June 2019, and Circular No. 24/A of 23 July 2021, which superseded the first) exempt changes in the promoter's internal shareholding or constituents that do not affect its obligations to allottees, conversion of a firm into an LLP or company, and a proprietorship passing to legal heirs. A voluntary merger of a company holding registered projects is treated as a transfer, with narrow exceptions. Where a lender enforces its security, the directions as law firms summarised them dispense with prior consent but require the allottees and MahaRERA to be told within seven days and an undertaking to honour the existing agreements for sale.

Red flag. A structure chosen to avoid the consent while changing what buyers were promised. Commentators have pointed out that the directions do not say clearly whether a sale of the whole shareholding to an outsider is "internal", so a share deal leaning on that exemption needs a written opinion, not an assumption.

Step 3. Price the registered date, not your own

Action. Model the remaining work against the current completion date on the registration. Section 15(2) makes you independently responsible for the outgoing promoter's pending obligations under the Act and under its agreements for sale, and its proviso says a transfer gives you no extension of time and leaves you liable for breach or delay.

What you will see. A gap between your schedule and the registered date, priced as delay interest to allottees and as the cost of applying for an extension on a record that already shows the seller's. How that application is read is in extensions under MahaRERA. The forum where allottees press a delay is busy: MahaRERA disposed of 6,945 complaints in 2025, up from 3,824 in 2024, and received 5,039 new ones, according to figures it released on 5 January 2026.

Red flag. A term sheet that assumes the regulator will reset the dates once a stronger promoter arrives. The Act says the opposite.

Step 4. Settle the lender and the accounts before the consents

Action. Agree the charge with the outgoing promoter's lender. A mortgage on the land does not lapse because the promoter changes, so the lender's agreement is part of the deal, not a formality after it. Then agree how the project's RERA accounts move to your control. Section 4(2)(l)(D) ring-fences 70 percent of allottee money for this project's land and construction cost, so that balance belongs to the project, not to the seller's exit price; the three-account regime sets out how the accounts work.

What you will see. A lender who wants your covenant in place of the seller's, and an account balance you can reconcile to the latest Form 3. Neither section 15 nor the published summaries of MahaRERA's circulars spell out the account mechanics, so write them into the transfer agreement.

Red flag. A withdrawal in the weeks before closing that the last Form 3 does not support, or a charge the lender has registered that the filing does not declare. Who holds the charge shows how the register records lenders, and construction finance for developers covers the new lender's file you will be building next.

Step 5. Collect consents that will survive a challenge

Action. Ask each allottee for written consent once the incoming promoter is named and its undertaking drafted: unchanged dates, price and specifications. Get every named co-allottee to sign. Count against the allottee list, not against the forms collected, and remember the promoter's own unsold flats do not count either way. Keep any change to the plans on a separate form, because altering sanctioned plans is a different decision with its own consent. What a buyer should ask before signing is set out in the buyer's side of section 15.

What you will see. With 96 allottees, 64 valid consents. With 94, after two cancellations, 63.

Red flag. Consents collected before the incoming promoter was named, signed by one of two joint owners, or bundled with a plan change.

Warning

A consent file stays live for years. One Mumbai change of promoter was approved by MahaRERA in 2021; the Maharashtra Real Estate Appellate Tribunal reversed that approval on 25 August 2026, finding the promoters had relied on invalid or contested buyer consents, and imposed a penalty of 2 percent of the project cost; the Bombay High Court set the tribunal's order aside on 29 September 2026 after the parties said they had settled. Collect every consent as though a tribunal will read it.

Step 6. File the application and the undertaking

Action. The outgoing promoter applies with the consents. Under Circular No. 24/A of 23 July 2021, the incoming promoter submits the documents listed in the circular's Annexure B and a declaration in the prescribed format, and uploads a registered undertaking that it will comply with every obligation under the agreements for sale the earlier promoter signed.

What you will see. Law-firm summaries of the circular report an order within a month of the application: approval with or without conditions, or rejection.

Red flag. Completing the commercial transfer before the order. Until MahaRERA approves, the outgoing promoter is still the promoter on the register and in law.

Step 7. Take over the filing, not just the site

Action. Once the order is passed, have the registration's details corrected to show you as promoter, re-declare the charges as they now stand, file your appointments of architect, engineer and chartered accountant, and diarise the next quarterly progress report. The deadlines are in the MahaRERA compliance calendar.

What you will see. The same registration number with a new promoter on it, and its history unchanged: the first promised date, the extensions, the complaints.

Red flag. A first quarter missed while the team settles in. It is the first filing a buyer reads under your name.

From the decision to transfer to the new promoter on the register
  1. 1

    1. Read the registration

    Status, dates, extensions, complaints, declared charges and the seller's record, before any term sheet.

  2. 2

    2. Fix the structure

    Assignment, share purchase, merger or lender enforcement; decide whether section 15 applies and take advice where the directions are unclear.

  3. 3

    3. Price the registered date

    Section 15(2) gives no extra time; the gap to your own schedule is a cost you inherit.

  4. 4

    4. Lender and accounts

    The land mortgage and the RERA accounts are settled in writing before allottees are asked.

  5. 5

    5. Two-thirds consent

    Written consent of two-thirds of the allottees, excluding the promoter, with the incoming promoter named.

  6. 6

    6. Application and undertaking

    Annexure B documents, a declaration and a registered undertaking under Circular No. 24/A of 23 July 2021.

  7. 7

    7. MahaRERA's order

    Approval with or without conditions, or rejection, reported as within a month.

  8. 8

    8. Registration corrected

    The new promoter's details on the same registration, charges re-declared, the next quarterly report filed on time.

Source: RERA Act, 2016, section 15; MahaRERA Circular No. 24/A of 23 July 2021 as summarised by law firms in 2021

An analogy: novation

In commercial contracts you can assign the benefit of a contract on your own, but to pass on the burden you need the other side to agree. That is novation, and it is why a supplier cannot hand a customer's contract to a stranger mid-way. Section 15 is a novation with every allottee as a counterparty, decided by two-thirds of them, and with the regulator's approval as a second signature. The new party steps into the old contract as written.

Anita Rao's take-over file

Anita Rao (our illustrative BD head at a mid-size developer scouting MMR and Pune micro-markets) was asked to size a smaller promoter's registered project in Pune district: two towers, 160 flats, 96 of them allotted, the first tower at its eleventh slab and the second at plinth. The registration read Active, carried one earlier extension, and declared a charge to a housing finance company. Names and numbers in this story are illustrative.

Her firm bids at the number that survives a four-quarter slippage stress, so she ran the stress from the registered completion date, 14 months away, not from the firm's own 26-month schedule. The 12 months between the two became a cost line before the first meeting with the seller's lender.

The snag was the consent count. The seller produced 67 signed forms against 96 allottees, three more than the 64 needed. Reconciled against the ledger, five forms carried only one of two co-allottees' signatures and two came from bookings cancelled since, which also brought the allottees down to 94 and the requirement to 63. That left 60 valid forms. The firm wrote to the missing co-allottees with the incoming undertaking attached, and the file went to MahaRERA with 66.

What the register shows about the target

The free project page is the place to begin, and the developer directory lists every registration filed under the seller's name. ReraGenie's Rs 2,999 project analysis assembles the rest of the read for one project:

  • The promoter's record: its registrations and how they ended, a concurrency timeline, complaints, litigation and appeals, and its self-declared pre-RERA projects worded as declared, never verified. The past projects you declared explains how to read that last table.
  • The date you would inherit, in context: the district's distribution of possession slip with the project's position in it and the count stated.
  • Whether the unsold stock can sell: the registered projects within 2 km and 5 km with their supply, and an absorption cross-section of sold share against project age, many projects photographed on one day and never a sales history.

While the deal is open, a Rs 299 project watch emails you when the target's filing changes, so an extension, a new complaint or a re-declared charge reaches you before the closing call rather than after it. Start from the target's free page.

Checklist before you sign the transfer agreement

  • Registration status, dates, extensions, complaints and declared charges read and priced.
  • Structure decided, with a written opinion if you are relying on an exemption.
  • Remaining work modelled against the registered date, with the gap costed.
  • Lender's agreement on the charge, and the RERA account balance reconciled to the last Form 3.
  • Consents counted against the allottee list, every co-allottee signed, no plan change bundled in.
  • Annexure B documents, the declaration and a registered undertaking ready to file.
  • Commercial completion conditional on MahaRERA's order.
  • First quarterly report, charge declaration and certifier appointments diarised.

For the reverse view, a landowner or seller reading you as the counterparty, see a landowner's diligence on a developer.

Methodology and sources

  • RERA Act, 2016, section 15 (consent, approval and the proviso on time) and section 4(2)(l)(D) (the 70 percent account).
  • MahaRERA Circular No. 11/2017 of 8 November 2017; the circular of 4 June 2019; Circular No. 24/A of 23 July 2021, as summarised by Cyril Amarchand Mangaldas, Conventus Law, Mondaq and Bar and Bench.
  • MahaRERA's January 2025 action on lapsed projects, as reported by Moneylife, January 2025.
  • The Mumbai change of promoter: the tribunal order of 25 August 2026 and the Bombay High Court order of 29 September 2026, as reported by Outlook Business, Sahi and Constro Facilitator.
  • ReraGenie analysis of 56,194 published MahaRERA projects, as updated on 11 October 2026; charge rates over the 17,664 projects that answer the charge question.

This article is educational and not legal advice. Confirm the position for your project with your advocate and the authority concerned.