Bank of Baroda Research put banks' commercial real estate credit at Rs 6.7 lakh crore at July 2026, Business Today reported on 10 September 2026, with banks adding Rs 42,142 crore between March and July while NBFC credit to the segment contracted by Rs 4,284 crore. Construction finance for developers is a large market whose recent growth has come from banks, and since 1 October 2025 it runs under new rules: the Reserve Bank of India (Project Finance) Directions, 2025 changed what a lender sets aside while your tower is built and what each quarter of slippage costs it. The credit file still asks for title, approvals, cost and progress, and most of the sworn answers are already public in your MahaRERA registration.
Key takeaways
- Under the Reserve Bank of India (Project Finance) Directions, 2025, in force from 1 October 2025, a lender holds a 1.25 percent standard provision on an under-construction commercial real estate loan and 1 percent on commercial real estate (residential housing).
- Each quarter a completion date is deferred adds a further provision, reported at 0.5625 percent a quarter for non-infrastructure projects, so the date in your term sheet is a pricing input.
- Loans whose projects reached financial closure before 1 October 2025 stay on the older norms unless there is a fresh credit event or a material change in terms.
- Title, approvals, cost, withdrawals and progress are already sworn in the MahaRERA registration: the legal title report, permission documents, Forms 1 to 3 and quarterly progress reports.
- Of the 17,540 published MahaRERA projects that answer the charge question, 2,663 (15.2 percent) declare a charge, as updated on 7 October 2026; once you borrow, your lender belongs in that declaration.
What you need before you start
- The registration number and the project's public page, on MahaRERA and on ReraGenie's project pages.
- The latest Forms 1, 2 and 3, the latest quarterly progress report, and the estimated cost you filed at registration.
- The lender's draft term sheet, especially its completion date.
- Your architect's area statement, split into residential and non-residential FSI.
- The title documents behind your legal title report.
The steps
Step 1. Find out which bucket the loan sits in
Action. Ask how the lender will classify the loan. Since June 2013 RBI has treated loans to builders for residential housing projects, other than for captive consumption, as commercial real estate (residential housing), CRE-RH. An integrated project with shops or a school still qualifies while that commercial area stays within 10 percent of total FSI; past that, the whole loan is commercial real estate.
What you will see. A construction-phase provision of 1.25 percent for commercial real estate and 1 percent for CRE-RH. On an illustrative Rs 150 crore loan that is Rs 1.875 crore against Rs 1.5 crore for the same building, and a lender prices what it must hold.
Red flag. A retail podium or commercial club added late in design that carries non-residential area past the 10 percent line. Your registration declares the project's type and, where filed, its unit mix, so the credit team sees it first.
Step 2. Set a completion date you can keep, and make the two dates agree
Action. Put the lender's proposed completion date beside the date you declared to MahaRERA. The directions measure delay against the date of commencement of commercial operations fixed at financial closure. For non-infrastructure projects, which include both kinds of real estate, law-firm summaries report a two-year ceiling on total deferment and an extra provision of 0.5625 percent for each quarter deferred, reversed once operations begin.
What you will see. On the same illustrative Rs 150 crore CRE-RH loan, the standard provision is Rs 1.5 crore and each quarter of deferment adds about Rs 84.4 lakh. Four quarters add Rs 3.375 crore, so a one-year slip takes what the lender holds from Rs 1.5 crore to Rs 4.875 crore, more than three times as much. Illustrative arithmetic, not any lender's pricing.
Red flag. A term-sheet date earlier than your RERA date promises the bank what you did not swear to the regulator; a later one says you plan to miss your buyers' date. Your project's free page on reragenie.com shows the first promised possession date against the current one and every extension with the reason you gave, which is the page a credit analyst opens before your meeting. Extensions under MahaRERA covers moving a date without damaging that record.
Step 3. Answer title and land from the declaration you already made
Action. Send the legal title report you uploaded at registration, not a fresh summary. Section 4(2)(l)(B) of the RERA Act made you declare the land free from all encumbrances or give details of them, including any other party's rights, title or interest, and the filing names the landowners.
What you will see. Law-firm summaries report that, outside infrastructure built under public-private partnership, at least 75 percent of the land or right of way must be available before disbursement. Your filing answers that first.
Red flag. A title report exception the lender's advocate finds before you mention it, or a landowner in your development agreement missing from the filing.
Step 4. Show the permission chain in order
Action. List the approvals in the order granted: layout, building plan, commencement certificate.
What you will see. Each project page on reragenie.com shows whether the legal title report, layout approval, building plan approval, commencement certificate and occupancy certificate slots hold a document, with its upload date. An upload is not proof the permission was granted.
Red flag. A commencement certificate covering some floors while the loan finances the whole tower.
Step 5. Put the money story through Forms 1, 2 and 3
Action. Reconcile the lender's means-of-finance table against your Form 3.
What you will see. Section 4(2)(l)(D) of the RERA Act puts 70 percent of allottee money into a separate scheduled-bank account for land and construction cost, and rule 5 of the Maharashtra rules releases it against the architect's Form 1, the engineer's Form 2 and the CA's Form 3, a rhythm set out in running the 70 percent account. For projects registered from 1 July 2024, MahaRERA's Order No. 56/2024 splits collections across Collection, Separate and Transaction accounts and keeps the first two clear of third-party encumbrances, so your lender's charge sits on the Transaction account and on collateral outside them: see the three-account regime for promoters and, from the lender's side, the regime and lender security.
Red flag. Withdrawals running ahead of the completion Forms 1 and 2 certify, or a registration cost estimate your current cost-to-complete no longer resembles.
Step 6. Let the quarterly progress reports carry the progress
Action. Give the lender's independent engineer your filed quarterly reports alongside the site data.
What you will see. Building-wise progress against the RERA activity checklist and, where filed, units booked. MahaRERA shows the current filing only, so keep your own copy of every quarter for the lender. Deadlines are in the MahaRERA compliance calendar.
Red flag. A quarterly report and the independent engineer's report for the same quarter giving different percentages.
Step 7. After sanction, declare the charge
Action. Once the security is created, update the registration so the encumbrance details name the lender and the amount.
What you will see. As updated on 7 October 2026, 2,663 of the 17,540 published projects that answer the charge question (15.2 percent) declare one: 478 of 3,468 answering 2025 registrations (13.8 percent) and 318 of 3,048 in 2026 to date (10.4 percent). Each is declared secured lending, counted over the projects that answered.
Red flag. A charge your lender has registered that your filing does not declare. It is the omission the lender is certain to find, because it is looking for its own name.
About 69 percent of published projects leave the charge question unanswered. An unanswered filing never means the land is free of charges, and a lender will not read it that way. Answer it, and keep it current as charges are created and released.
Source: ReraGenie analysis of declared charge rows across 56,091 published MahaRERA projects, as updated on 7 October 2026. Any rate uses the 17,540 projects that answered the charge question.
The 43 rows held by an asset reconstruction company or the SWAMIH fund are a fact about the holder, never a verdict on the project.
An analogy: the data room the regulator made you build
In an acquisition the seller builds a data room once and every bidder reads it. Your MahaRERA registration is a data room the regulator required you to build: public, sworn by you and your certifying professionals, and dated. A lender's diligence is one more bidder walking in. A fresh pack gets reconciled against the room, and every difference becomes a question. Send the filed documents first, with a reconciliation note. What MahaRERA filings tell a developer sets out what else is in it.
Anita's file, and the one snag
Anita Rao (our illustrative BD head at a mid-size developer scouting MMR and Pune micro-markets) is raising construction finance for her firm's new Pune tower. The firm already bids at the number that survives a four-quarter slippage stress, so she set the lender's completion date to match the date declared on MahaRERA, and opened her pack with the filed title report, the permission documents and the last Form 3.
The snag came from design. A late revision had added ground-floor retail that took non-residential area to about 12 percent of FSI, and the lender's credit team classified the loan as commercial real estate. The firm trimmed the retail to about 8 percent in a revised plan, and the lender reclassified the loan as residential housing, on which it holds 1 percent rather than 1.25 percent during construction. Names and numbers in this story are illustrative.
The lender's ask, and the filing that answers it
| The lender asks | The filing that answers | What the filing does not answer |
|---|---|---|
| Clear title, land available | Legal title report, landowners, the section 4(2)(l)(B) declaration | A current search and the lender's own advocate's opinion |
| Approvals in place | Uploaded layout, plan and commencement certificate | Whether each was granted as uploaded, for every floor |
| Cost and means of finance | Registration cost estimate and Form 3 | Today's cost-to-complete and equity outside the accounts |
| Progress against plan | Forms 1 and 2, quarterly progress by building | Earlier quarters, once replaced |
| Completion date and delays | Declared possession date, extensions with reasons | The term-sheet date, unless you align it |
| Existing borrowing | Declared charges with lender and amount | Anything unanswered, which never proves no charge |
What the project analysis adds for this file
A lender reads your project, then your market and your record. ReraGenie's Rs 2,999 project analysis assembles the last two around your filed location: the registered projects within 2 km and 5 km with their supply, plus an absorption cross-section of sold share against project age, many projects on one day and never a sales history; the district's distribution of possession slip with your position and the count stated, the evidence behind the date you are about to sign; and the promoter's record, its registrations, how they ended, and a concurrency timeline. What RERA filings tell a lender describes the same reading from the other desk; the project analysis assembles it before your meeting.
Checklist before you send the pack
- Classification agreed, with the area statement showing the commercial share.
- Term-sheet completion date matched to, or reconciled with, your MahaRERA date.
- Filed title report, landowner table and encumbrance declaration, not summaries.
- Permissions in order, with the commencement certificate's floor coverage stated.
- Form 3 reconciled to the means-of-finance table; Forms 1 and 2 to the engineer's report.
- Your own archive of every quarterly report, and a note to declare the charge after sanction.
Methodology and sources
- Reserve Bank of India (Project Finance) Directions, 2025 (issued 19 June 2025, effective 1 October 2025); deferment, grandfathering and land figures as reported by law firms in 2025.
- RBI's CRE-RH classification, June 2013. Bank of Baroda Research, reported by Business Today, 10 September 2026.
- RERA Act sections 4(2)(l)(B) and 4(2)(l)(D); Maharashtra RERA Rules, rule 5; MahaRERA Order No. 56/2024.
- ReraGenie analysis of 56,091 published MahaRERA projects, as updated on 7 October 2026. Loan figures are illustrative.
This article is educational and not legal advice. Confirm the position for your project with your advocate and the authority concerned.
Evaluating a micro-market or a land parcel?
The ReraGenie project analysis reads the filings around your parcel: supply, absorption and promoter records. Rs 2,999 per project; the area market report is a flat Rs 2,999 per pincode.
See the project analysis