Of the 4,171 Nashik district registrations that file both a first and a current promised possession date, 437 now promise possession later than they first did. That is 10.5 percent, against 22.8 percent across Maharashtra. Read through MahaRERA's register, the Nashik property market is one where projects have moved their dates less often than the state's, lapsed less often and drawn fewer complaints, while the newer projects on sale today report a smaller share of their units sold. The register cannot say why, but it can show where each of those patterns sits.

Key takeaways

  • As updated on 7 October 2026, Nashik district has 4,172 MahaRERA registrations, and 3,897 of them (93.4 percent) are filed in Nashik taluka.
  • 18.3 percent of Nashik's registrations are Lapsed, against 24.8 percent statewide, and 10.5 percent now promise possession later than they first did, against 22.8 percent.
  • 11.0 percent of Nashik registrations carry an extension granted on application and 3.0 percent at least one complaint, against 23.8 and 12.8 percent statewide.
  • Active Nashik projects that file unit counts report 25.0 percent of their 58,035 units sold or booked, against 37.6 percent for Active projects statewide.
  • PropEquity counted 11,188 homes sold in Nashik in 2025, 10 percent fewer than the 12,492 sold in 2024.

The question this data answers

Nashik is usually discussed through what is coming to it: the Simhastha Kumbh Mela, whose flag hoisting was scheduled for 31 October 2026, and the Samruddhi expressway, whose last stretch, from Igatpuri to Amane, opened on 5 June 2025 and completed the 701 km road between Nagpur and Mumbai. The register answers questions closer to a buyer's decision: where the registered projects are, which body sanctioned them, how those registered since 2017 have ended, and how much of what is on sale now has sold. It files no prices, so it cannot say what anything costs.

Where the projects are

Nashik district's market is largely one city. Of its 4,172 registrations, 3,897 (93.4 percent) are filed in Nashik taluka, which holds the city. Igatpuri, on the expressway towards Mumbai, has 77, Niphad 68, Sinnar 51, Dindori 28 and Malegaon 27; every other taluka has fewer than ten. These are the seven pincodes with the most registrations.

PincodeLocalities most often filedRegistrationsActiveRegistered 2025 and 2026
422003Panchavati, Adgaon, Makhmalabad80820384
422010Pathardi, Pathardi Phata49111856
422009Indira Nagar, Govind Nagar47010449
422101Nashik Road, Jail Road, Deolali36511128
422013Gangapur Road, Anandwali2596419
422004Mhasrul1874420
422005Gangapur Road, College Road1314728

In ReraGenie's analysis of the published registrations, 422003, whose filings most often name Panchavati, Adgaon and Makhmalabad, leads on all three counts, and Pathardi's 422010 is second on all three. New registrations do not follow the old pattern exactly: 422005, around Gangapur Road and College Road, registered as many projects in 2025 and 2026 as Nashik Road's 422101, though its total is 131 against 365. Gangapur Road is filed under two pincodes, a reminder that a filed locality is the promoter's description, not a boundary.

What is being built, and how much

Nashik district registrations by year(projects registered each year, all statuses; 2026 to 7 October)
2017728
2018240
2019353
2020377
2021529
2022714
2023534
2024254
2025282
2026161, to 7 October

Source: ReraGenie analysis of 4,172 published MahaRERA registrations in Nashik district, as updated on 7 October 2026

The 2017 figure is large because projects already under way had to register when the law took effect. After that, registrations climbed to 714 in 2022, then fell to 534 in 2023 and 254 in 2024. Comparing the same eight months of each year, January to August, and counting only projects that file Nashik as their district, Nashik registered 409 projects in 2023, 194 in 2024, 199 in 2025 and 135 in 2026, the lowest of the four. New projects in Maharashtra in 2026 sets this year's count beside other districts'.

Nashik registers flats, not plots. 2,685 registrations are filed as residential or group housing, 262 as commercial, 141 as mixed and 1,057 under "others"; only 27 are filed as plotted, and only 46 (1.1 percent) carry a plotted layout's table, against 3,294 statewide. That is the opposite of the Nagpur property market, where about 45 percent of projects are plotted. A Nashik buyer's questions are mostly a flat buyer's: the building's commencement certificate, its construction progress and its possession date.

Who sanctions building

1,163 Nashik registrations name the body that sanctioned them in the filing's free-text box, and naming it is recent: 4 percent of 2017's registrations do, 51 percent of 2023's and 89 percent of 2025's. Of those that name one, the Nashik Municipal Corporation, in its various spellings, accounts for about 974 (83.7 percent), and the Nashik Metropolitan Region Development Authority for 42 (3.6 percent). Sinnar Municipal Council follows with 13, the Deolali Cantonment Board and the Malegaon Municipal Corporation with 11 each, and the Igatpuri and Ozar municipal councils with a handful each. Eight filings give only the initials "NMC", and we leave them unassigned rather than guess which body is meant.

Where Nagpur's projects are split between three main sanctioning bodies, Nashik's filings point mostly to one. Inside the corporation's limits the state's building code adds a short chapter of Nashik rules, which Nashik's building rules reads; outside them, only the body named on the filing can confirm a permission.

How projects have delivered

MeasureNashik districtMaharashtra
Registrations4,17256,091
Completed2,286 (54.8%)21,679
Active1,090 (26.1%)19,927
Lapsed764 (18.3%)13,897 (24.8%)
De-Registered31500
Revoked081
Promise possession later than they first did10.5%22.8%
At least one extension granted on application11.0%23.8%
At least one complaint3.0%12.8%

On lapses, dates, extensions and complaints, Nashik's registrations read better on the register than the state's. Its Lapsed share is 18.3 percent against 24.8, and the gap holds in four of the five registration years shown below. 2023's registrations are the one year where Nashik's share is higher.

Share of registrations now Lapsed, by year of registration(percent of each year's registrations)
2017 Nashik17.3%
2017 Maharashtra29.2%
2019 Nashik19.8%
2019 Maharashtra34.2%
2021 Nashik22.7%
2021 Maharashtra35.6%
2022 Nashik22.7%
2022 Maharashtra29.1%
2023 Nashik20.6%
2023 Maharashtra19.7%

Source: ReraGenie analysis of published MahaRERA registrations, Nashik district against the state, as updated on 7 October 2026

Dates have moved less too. 10.5 percent of Nashik registrations promise possession later than they first did, against 22.8 percent statewide, and 11.0 percent carry an extension granted on application, against 23.8 percent. MahaRERA's possession delay data and RERA extension data read those two measures across the state. Complaints are rarer: 125 Nashik registrations, 3.0 percent, carry at least one, against 12.8 percent statewide. The register records that a complaint was filed, not why, so it cannot say whether a low share means fewer problems or fewer buyers who chose to complain. No Nashik registration has been revoked, and 31 are De-Registered, the status lapsed, revoked, deregistered explains.

Declared charges follow the same pattern. Of the 1,018 Nashik registrations that answered the filing's question on charges, 67 (6.6 percent) declared one, such as a lender's mortgage over the project, against 15.2 percent of the 17,540 that answered statewide; what MahaRERA's declared charges show explains why a filing that did not answer must never be read as a clean one. A row of bank logos on a brochure is a different thing again, as bank approved project explains.

What is selling

843 of Nashik's 1,090 Active projects file unit counts. Together they carry 58,035 units, of which 14,508 are reported sold or booked: 25.0 percent, against 37.6 percent for Active projects statewide. The typical project is small, with a median of 45 units.

Active Nashik projects: share of filed units sold or booked, by year of registration(percent of units; number of projects filing unit counts in brackets)
2022 (78 projects)35.6%
2023 (139 projects)34.8%
2024 (148 projects)24.6%
2025 (246 projects)11.8%
2026 (161 projects)0.4%

Source: ReraGenie analysis of 843 Active Nashik projects filing unit counts, as updated on 7 October 2026; units sold or booked as filed in the building table

Read the sold share by age before reading it as demand. A project's sold count starts near zero and grows only as the promoter updates the filing, and 246 of the 843 were registered in 2025 and 161 in 2026. Those registered in 2022 and 2023 report about a third sold or booked. Registrations of 2025 and 2026 promise possession a median of 40 months after registering, so much of today's Active stock will be on sale for years yet.

Outside the register, sales slowed. PropEquity counted 11,188 homes sold in Nashik in 2025, 10 percent fewer than the 12,492 of 2024, in its full-year report on 15 tier-II cities, as reported by PTI on 12 February 2026.

What is coming, and on whose dates

Public works are arriving in Nashik on timetables of their own. The Nashik-Trimbakeshwar Kumbh Mela Authority has given administrative sanction to infrastructure and security works worth Rs 9,600.30 crore, according to the Ministry of Tourism's reply to a question in Parliament in January 2026, ahead of a Simhastha whose main bathing days fall in August and September 2027. Progress is uneven: in September 2026 the Free Press Journal reported that about 70 percent of the work remained on 35 major road and bridge projects due by March 2027. The expressway, by contrast, is open, and Igatpuri, where its last stretch begins, holds the district's largest cluster of registrations outside Nashik taluka. None of this is in a project's filing: a brochure that leans on the Kumbh roads or a future metro is describing public works with their own owners and dates.

An analogy: the smaller station's board

Reading Nashik against the state is like reading a smaller railway station's punctuality board beside a big junction's. Fewer trains run late and fewer passengers complain, but each train also fills more slowly. The board records what happened on each run. It does not say whether the line is better run or simply less crowded.

Priya and Arjun run the checks for Arjun's parents

Priya and Arjun (illustrative, as our stories always are) spent months on the register before booking their Pune flat, and the habit has found a second use. Arjun's parents live in Nashik and are thinking of moving to a smaller, newer flat there, so the couple added a tab to their spreadsheet and ran the same checks on three projects his parents had liked.

The first was Completed, and its permission chain showed the occupancy certificate slot holding a document, which told them what to ask for, not that the certificate had been granted. The second was Active with its first promised date unmoved, but that date was more than three years away, longer than his parents wanted to wait. The third had left the charges question unanswered, so Priya drafted a letter to the promoter asking whether any lender held a charge over the land. Names and numbers in this story are illustrative.

Warning

A blank answer is not a clean one. Only 1,018 of Nashik's 4,172 registrations answered the declared-charges question, and a filing that did not answer says nothing about whether a lender holds a charge over the land. Ask the promoter in writing, and read the legal title report and the exceptions it attaches, before you pay a booking amount.

If you are looking in Nashik, every registration has a free ReraGenie page with its full filing, including the permission chain and any declared charges, and district alerts for Nashik email new registrations as they appear, free during the pilot beta.

What this means for you

  • Read the age before the sold share. A Nashik project registered in 2025 or 2026 will show few sales whatever its demand; one registered in 2022 showing the same is a different fact.
  • Read the body, not the address. Only the sanctioning body named on the filing can confirm a permission, and outside the corporation's limits that may be the metropolitan authority, a council or the cantonment board.
  • A district average is not a project's record. Nashik's lower lapse and delay shares say nothing about the project in front of you; its own possession story, the people behind its promoter and the promoter's other registrations do.

What the report adds for one project

ReraGenie's free Nashik district page lists every registration in the district. The Rs 499 buyer report reads one project against that background: its construction pace against the district's, its possession story from the first promised date to the current one, and the projects within 2 km of it and how each has ended. Land and title are answered as five questions, including whether the land is mortgaged as filed and what the legal title report concludes, with the exceptions it attaches.

Methodology and sources

  • ReraGenie analysis of 56,091 published MahaRERA registrations, 4,172 of them naming Nashik as their district, as updated on 7 October 2026. Talukas, pincodes, localities and project types are as filed; registrations that file no district are not counted here. Years are by registration date, and 2017 includes ongoing projects that registered when RERA began.
  • Sanctioning bodies are read from the filing's free-text field, with spellings of one body counted together; 1,163 Nashik registrations name one, and the 8 giving only "NMC" are left unassigned.
  • Date revisions compare the first filed completion date with the current one, for the 4,171 Nashik registrations filing both. Extensions count those granted on application. Sold or booked shares count units in Active projects that file the building table.
  • Declared charges are counted over the registrations that answered the question (1,018 in Nashik, 17,540 statewide), never over the district.
  • Sales: PropEquity's full-year 2025 report on 15 tier-II cities, as reported by PTI on 12 February 2026.
  • Simhastha Kumbh Mela: dates as announced by the state government and reported by PTI on 1 June 2025; administrative sanction from the Ministry of Tourism's reply in Parliament, January 2026; progress from the Free Press Journal, September 2026.
  • Samruddhi expressway: final stretch, Igatpuri to Amane, opened on 5 June 2025, as reported by PTI.
  • Metro: Swarajya, June 2026, and the Free Press Journal, 2026.