A GujRERA extension is the Gujarat register's record of a project asking for more time. When a promoter cannot finish by the completion date it filed at registration, it applies to the Authority to extend the registration, and the approved extension moves the date the project is registered until. As updated on 15 November 2026, 2,822 of the 17,399 registrations ReraGenie reads have extended at least once, most of them by exactly a year. The extension is easy to find once you know where to look, and it says more about a project than any brochure's possession date.
Key takeaways
- 2,822 of 17,399 GujRERA registrations, 16.2 percent, list at least one extension application; 633 list two or more.
- The typical move is a year: 1,488 of the 2,189 projects with one extension moved their completion date by exactly twelve months.
- 2,204 of 3,656 extension applications were made after the project's original completion date had already passed.
- An extension moves the date the project is registered until. Your rights under section 18 still run from the date in your agreement for sale.
Where an extension shows on the register
Two places on a project's GujRERA page record it. The first is the registration number itself. An extended project's current number carries a mark such as EX1 or EX2 before its last part, as in .../RAA00456/EX1/010220. 2,706 of the registrations ReraGenie reads carry an EX mark in their current number.
The second is the applications list, which records each extension as its own application with the date it was applied for and the date it was approved. 2,822 registrations list at least one, 3,656 applications in all. The two counts differ slightly because a project's number does not always carry the mark when its applications list does. Read the list: it carries the dates.
The project page also files two completion dates: the original one, from registration, and the current one, extensions included. On 2,867 registrations the current date is later than the original, and 2,821 of those list an extension application. The other 46 moved their date with no extension on the list, and are worth a question to the promoter. How to find each of these on the portal is in checking a project on the GujRERA portal.
How far a project moves
Source: ReraGenie analysis of GujRERA registrations, original against current completion date, as updated on 15 November 2026
A year is the normal unit. 2,189 projects have one extension, and 1,488 of them moved by exactly twelve months; 213 moved by six and 105 by nine. Among the 480 projects with two extensions, the commonest total is 24 months, on 188 of them. 153 projects list three or more extensions, and 100 have moved their date by more than three years in all.
Section 6 of the RERA Act lets the Authority extend a registration for force majeure, and in reasonable circumstances where the promoter is not at fault, for up to a year in aggregate. The register shows extensions well beyond a first year, so it records later grants too; it does not say under which provision each one was made.
How often, by year of registration
Source: ReraGenie analysis of GujRERA registrations, as updated on 15 November 2026
Read this the way you would read any count that depends on time passing. A project registered in 2024 has rarely reached its completion date yet, so it has had little reason to extend. The fairer measure counts only the 10,459 projects whose original completion date has passed: 2,813 of them, 26.9 percent, have extended. So roughly one project in four that reached its first date asked for more time.
By district, on all registrations, Vadodara stands out at 23.1 percent (673 of 2,908) and Valsad at 22.8 percent, against 14.6 percent in Ahmedabad, 15.6 percent in Surat, 15.5 percent in Gandhinagar and 13.5 percent in Rajkot. Vadodara also leads on missed quarterly returns, as GujRERA quarterly returns in default sets out.
Applied for late, approved in weeks
An extension applied for before the date passes is planning. One applied for after it is catching up. Of the 3,656 extension applications, 2,204 were made after the project's original completion date had already passed, and 1,452 before it. A project in the first group spent a stretch past its filed date with no extension in place, which is exactly when its final quarterly return falls due and when a buyer reading the register would have seen a date in the past.
Once applied for, approval is usually quick. On the 3,482 applications that file both dates, the median wait was 47 days; a quarter were approved within 24 days and three quarters within 80. 1,107 were approved within a month, and 194 took more than six months.
An extension is a decision about the registration, not about your agreement. Under section 18 of the RERA Act, your right to withdraw with a refund and interest, or to stay and be paid interest for every month of delay, runs from the possession date in your agreement for sale. Keep a copy of that page.
The other application: alterations
Beside extensions, the applications list records alterations: applications to change something in a registered project. 1,959 registrations list one, 2,074 in all, approved after a median of 69 days, with 127 still showing no approval date. 520 projects list both an extension and an alteration. The register does not say on the list what each alteration changed, so open the application on the portal. If it changes the plan of your flat or of the building, section 14 of the Act requires your consent for your flat and the consent of two thirds of the buyers for the building, and an approval on the portal does not stand in for either.
An analogy: the new time on the departures board
An extension is the new departure time on an airport board. It tells you when the airline now expects to leave, and it is worth knowing. It says nothing about what the airline owes you for the wait, which is set by the time printed on your ticket. Your agreement for sale is the ticket.
Hetal and Jignesh compare two dates
Names and numbers in this story are illustrative. One project on Hetal and Jignesh's shortlist, in Gota, had a registration number ending EX2 and two extensions on its applications list, each of a year, the second applied for four months after the first date had already passed. Its filed completion date was now December 2026, and the sales office's draft agreement said possession by the same month. Jignesh asked two things in writing: what had caused each extension, and that the agreement fix December 2026 as the possession date, with no clause letting it move with any later extension. The answer to the second decided the booking.
What ReraGenie's free page shows
Every GujRERA registration ReraGenie reads has a free page: the filed completion date as the date the registration is valid until, every extension applied for, how many units are recorded booked, construction stages by building, the cost lines, the approving authority, every filed document and, where the accountant's Form 3 lists one, each loan the project carries. A Gujarat buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now. Find a project from the Gujarat project list. How extensions work under the Act is in project extension under sections 6 and 7, what a buyer is owed when the date slips is in RERA rules for delayed possession, and filing a complaint with the Authority is in GujRERA complaint.
The one-line summary
One Gujarat project in four that reaches its completion date extends it, usually by a year and often after the date has passed: find the EX mark and the applications list, and hold the promoter to the date in your agreement.
Looking at a project in Gujarat?
ReraGenie publishes a free page for every GujRERA registration it covers: the filed dates, the approvals, the documents and the promoter's other registrations on the same register. A Gujarat buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now.
Browse Gujarat projectsCreate a free account to keep a shortlist you can open on any device.