A builder's earlier projects are the first thing most buyers want to know about, and GujRERA asks for them. Section 4(2)(b) of the RERA Act requires a promoter applying for registration to give brief details of the projects it launched in the past five years: their current status, any delay, cases pending, the type of land and payments pending. Gujarat's register files that list column by column. As updated on 15 November 2026, 8,830 of the 17,399 registrations ReraGenie reads carry one, 10,262 rows in all. It is useful, and it is a declaration, so read it the way you would read a CV.
Key takeaways
- 8,830 of 17,399 GujRERA registrations carry a declared list of the promoter's earlier projects, usually one row and at most 16.
- Of 10,262 declared rows, 4,736 say Completed, 4,919 Ongoing and 578 Delay; 4,679 of the Completed rows have a completion document attached.
- 527 of the 578 Delay rows file the delay as zero months, so the column marks a delay without measuring it.
- The list is filed on almost every registration from 2019 to 2023 and on few before or since: an empty list often reflects the year, not the builder.
What the list holds
Each row names an earlier project with its address, district and state, and then the columns section 4(2)(b) asks for:
| Column | What it says | Filled on |
|---|---|---|
| Status | Completed, Ongoing or Delay | every row |
| Type of land | Residential, Mixed Development, Commercial | every row |
| Months delayed | the promoter's figure for the delay | 621 rows |
| Completion document | whether one is attached | 4,718 rows |
| Cases pending | yes or no | 93 rows say yes |
| Payment pending | yes or no, with an amount | 203 rows say yes |
Most rows describe housing: 6,612 Residential, 2,522 Mixed Development and 1,124 Commercial. Almost all are in Gujarat; 24 rows name another state or union territory, Karnataka and Maharashtra the commonest.
Read Completed by its document
A row marked Completed is a claim. A row marked Completed with a completion document attached is a claim with paper behind it. 4,679 of the 4,736 Completed rows carry a document; 57 do not. Open the document on the portal: a building use permission or completion certificate from the planning authority is what you are looking for, and its date and building should match the project named.
Delay is marked, not measured
578 rows say Delay. 527 of them file the delay as zero months, 39 as one to six, 8 as seven to twelve and 3 as more than a year. So the column tells you a promoter admitted a delay and almost never how long it was. 588 registrations declare at least one delayed earlier project. A Delay row is a reason to find that project and ask its buyers when they got possession.
When the list was filed
Source: ReraGenie analysis of GujRERA registrations, declared earlier-projects list, as updated on 15 November 2026
The pattern is plain: the list sits on nearly every registration from 2019 to 2023 and on few before or since. The register does not say why. What it means for a buyer is that an empty list on a 2025 registration is ordinary and proves nothing, while an empty list on a 2020 registration, from a builder with a known history, is worth a question.
The register keeps a second list beside the declared one: the promoter's own registrations on GujRERA. The two do not always agree. On 85 registrations from 2019 to 2023, the declared list is empty while the register shows the same promoter holding other GujRERA registrations. Read both.
How to check what is declared
- Open the project on the GujRERA portal and read the promoter's earlier projects; checking a project on the GujRERA portal shows where.
- For each Completed row, open the completion document and match its building and date.
- Search each earlier project by name on GujRERA. A registered one has its own page, with its extensions on its applications list: extensions on GujRERA explains how to read them.
- For a Delay row, or one with cases or payments pending, visit the project and ask two or three residents when they got possession.
- Note the entity. A group often builds each project under a separate firm, so the earlier projects may sit under another name; what a builder's entity type tells you explains the shapes.
The general method, which works in any state, is in how to check a builder's track record, and checking the people behind the firm is in checking a builder's company and directors.
An analogy: the CV and the references
The declared list is a builder's CV. It names the past jobs, says which were finished and admits to a delay or two, and nobody checked it before it was printed. You do not hire on a CV alone. You call the references, and for a builder the references are the completion documents and the people living in the buildings.
Hetal and Jignesh read a declared list
Names and numbers in this story are illustrative. The builder of a project in Bopal declared three earlier projects: two Completed, each with a document, and one Delay, filed at zero months. Hetal opened the two documents and found that one was a building use permission for a different block from the one named. Jignesh drove past the delayed project on a Sunday; two residents said they had moved in fourteen months after the date in their agreements. Neither finding ended the search. Both went into the list of questions they took to the sales office.
What ReraGenie's free page shows
Every GujRERA registration ReraGenie reads has a free page: the filed completion date as the date the registration is valid until, every extension applied for, how many units are recorded booked, construction stages by building, the cost lines, the approving authority, every filed document and, where the accountant's Form 3 lists one, each loan the project carries. Each promoter also has a free developer page listing every GujRERA registration filed under the same name. Neither prints the declared earlier-projects list; read that on the GujRERA portal. A Gujarat buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now. Find a builder's projects from the Gujarat project list.
The one-line summary
GujRERA's declared list of earlier projects is the builder's own CV: trust a Completed row only with its document, treat a Delay row as a lead, and read an empty list against the year it was filed.
Looking at a project in Gujarat?
ReraGenie publishes a free page for every GujRERA registration it covers: the filed dates, the approvals, the documents and the promoter's other registrations on the same register. A Gujarat buyer report is on sale for most projects, and new-registration alerts are free; the project watch covers MahaRERA projects only for now.
Browse Gujarat projectsCreate a free account to keep a shortlist you can open on any device.