When cement's GST rate fell from 28 to 18 percent on 22 September 2025, the obvious question for a developer was how to claim the difference. There is nothing to claim. A developer selling flats at 1 or 5 percent pays that rate without input tax credit, so the GST on every bag of cement was never recoverable: it was cost. GST for real estate developers after that round is therefore a story about the cost stack rather than the ledger, and the saving is smaller than the headline. Here is what moved, what did not, and the purchase rule that still decides whether you pay extra tax at year end.

Key takeaways

  • Since 1 April 2019 residential apartments in a real estate project carry GST of 1 percent (affordable) or 5 percent (other) without input tax credit, under Notification 3/2019-Central Tax (Rate); Crisil's September 2025 read found those rates unchanged by the rate rationalisation.
  • Cement's rate fell from 28 to 18 percent from 22 September 2025, but a developer that cannot claim input tax credit gains only through a lower cost, and only if the supplier's pre-tax price holds.
  • If the pre-tax price holds, a cement bill including GST falls by about 7.8 percent; ICRA put cement at 10 to 12 percent of construction cost in rural housing, which makes the saving 0.8 to 1.0 percent of construction cost.
  • A promoter must buy at least 80 percent of inputs and input services from registered suppliers or pay reverse-charge tax at 18 percent on the shortfall, and cement from an unregistered supplier is taxed under reverse charge regardless.
  • Development rights, TDR, FSI and long-term lease premiums used for flats booked before completion are exempt; the share for flats unsold at completion is taxed under reverse charge, capped at 1 or 5 percent of their value.

Iqbal re-prices one tower

Iqbal (our illustrative Thane builder) runs three active projects and keeps a dashboard of QPR deadlines. In the week after the cut his purchase head reported that the lower cement rate would "come back as credit". His chartered accountant corrected him in one line: the firm sells at 5 percent without input tax credit, so the GST it pays on cement never came back and never will. The cut shows up in cost.

So Iqbal re-priced one of the three towers, not the redevelopment. Its construction budget was Rs 100 crore, with Rs 8 crore of cement before tax. At 28 percent the cement line was Rs 10.24 crore; at 18 percent it is Rs 9.44 crore. That is Rs 80 lakh, 0.8 percent of the budget, or about Rs 50,000 on each of the tower's 160 flats. The snag came within weeks: one dealer raised his pre-tax price per bag, and part of the saving went to him rather than to the tower. Names and numbers in this story are illustrative.

GST without input tax credit, in plain terms

Notification 3/2019-Central Tax (Rate), dated 29 March 2019, amended Notification 11/2017-Central Tax (Rate) so that from 1 April 2019 residential apartments in a real estate project carry 1 percent if affordable and 5 percent otherwise, without input tax credit. Affordable means two tests at once: a carpet area up to 60 square metres in the metropolitan cities, which for this purpose include the Mumbai Metropolitan Region and so Thane, or 90 square metres elsewhere, and a gross amount charged of no more than Rs 45 lakh. A flat sold after its completion certificate carries no GST at all. The buyer's side of the same rules is in GST on flats.

"Without input tax credit" means the GST you pay on cement, contracts and services cannot be set against the GST you collect from buyers. It is part of what the building cost.

An analogy: input GST behaves like freight. Nobody sends a buyer a separate bill for the freight on the steel. It is part of what the material cost to reach site, and it ends up inside your cost per square metre. Cut the freight rate and the stack gets cheaper; the rate you charge the buyer does not move. For a developer on the 5 percent rate, the cement cut is a freight cut.

Three rules that sit around the rate

The 80 percent purchase rule. The concessional rates come with a condition: at least 80 percent of a project's inputs and input services, by value, must come from registered suppliers. A short list is left out of the calculation, including development rights, long-term leases, FSI and fuels. On any shortfall the promoter pays tax under reverse charge at 18 percent, worked out for each financial year.

Cement from an unregistered supplier. Cement has a rule of its own. Where a promoter receives cement from an unregistered person, the notification makes the promoter pay tax on it under reverse charge "at the applicable rates", in the month it arrives, even if the 80 percent test is otherwise met. Because the wording points to the applicable rate rather than naming one, it reads as following cement's own rate, 28 percent before 22 September 2025 and 18 percent since; confirm the current position with your adviser.

Development rights, TDR, FSI and long-term lease premiums. The promoter is liable under reverse charge on these, but the part used for residential apartments booked before the completion certificate or first occupation is exempt. The share attributable to flats still unbooked at completion is taxed, capped at 1 or 5 percent of their value, as the GST Council's FAQ on the real estate sector sets out. A tower completing with a third of its flats unsold carries a reverse-charge bill on a third of its TDR. How that compares with buying premium FSI is in premium FSI or TDR, and how the same rights are taxed inside a joint development is in JDA tax and stamp duty.

What September 2025 changed, and what it did not

Cement moved from 28 to 18 percent with effect from 22 September 2025, and EY's September 2025 alert on the real estate and construction changes listed sand-lime bricks and some wood-based products moving from 12 to 5 percent. The residential rates did not move: Crisil's September 2025 note on the housing sector found the 1 percent affordable rate, the 5 percent under-construction rate and the exemption for completed property all unchanged.

The size of the saving is easy to overstate. If a supplier's pre-tax price holds, a cement bill including GST falls by 10 parts in 128, about 7.8 percent. ICRA, in September 2025, put cement at nearly 10 to 12 percent of total construction cost in rural housing and the resulting reduction at 0.8 to 1.0 percent of construction cost. CREDAI's reaction the same month made the other half of the point: the benefit reaches the cost stack only if cement makers and other manufacturers actually bring down their prices.

One illustrative tower's construction cost stack, before and after the cement cut(Rs crore, including GST paid on inputs)
Cement, before the cut (GST 28%)Rs 10.24 crore
Cement, after the cut (GST 18%)Rs 9.44 crore
Steel (assumed unchanged)Rs 14.16 crore
Other materials (assumed unchanged)Rs 30.60 crore
Labour and contracts (assumed unchanged)Rs 45.00 crore
Total, before the cutRs 100.00 crore
Total, after the cutRs 99.20 crore

Source: Illustrative: Rs 8 crore of cement before tax, GST at 28 percent before 22 September 2025 and 18 percent after, the supplier's pre-tax price held constant. Not a measured cost. Rate change: GST Council, effective 22 September 2025.

The two totals are almost the same bar, which is the point. Larger lines move for other reasons, among them the premiums that ride the ready reckoner.

Tip

Ask each cement supplier for its pre-tax price per bag on an invoice from before 22 September 2025 and one from after. If the pre-tax figure rose, part of the cut went to the supplier. That comparison, per supplier, is the saving that belongs in your pro forma.

Where developers get it wrong

  1. Expecting the cut back as credit. On the 1 and 5 percent rates there is no credit to receive.
  2. Assuming the buyer's rate moved. It did not. A flat booked after 22 September 2025 carries the same 1 or 5 percent as one booked before it.
  3. Treating cement as covered by the 80 percent test. Cement from an unregistered dealer is taxed under reverse charge in the month it arrives, even in a year that clears 80 percent.
  4. Leaving the 80 percent check to year end. A shortfall found in March is taxed at 18 percent on its whole value; tracked monthly, it is a purchasing decision.
  5. Treating TDR as exempt for every flat. The exemption follows bookings. Flats unsold at completion bring a reverse-charge bill on their share of the development rights, so the sales curve is also a tax schedule.

That last point is where the register helps. Your project's free page on reragenie.com shows the declared completion date and, where filed, the units booked, the two figures that size the reverse-charge bill on development rights at completion, and the district pages show what the projects around you have filed.

What the project analysis shows for this question

A re-priced cost stack is a number you then have to place. ReraGenie's Rs 2,999 project analysis gives three reference points for it: the district's distribution of cost per square metre, with your project's position and the count stated, so a revised estimate sits against the costs your neighbours filed; an absorption cross-section of sold share against project age, many projects photographed on one day rather than a sales history, which is the evidence for how much of a tower is likely to be unbooked at completion and so for the reverse charge on development rights; and completed projects' cycle time, which dates that liability. It is built from the filings and selected filed documents, and the filings carry no flat prices.

The one-line summary

The buyer's rates did not move; cement's did, and without input tax credit that is a cost cut of about a percent or less where suppliers pass it on, while the 80 percent rule and both reverse charges stand as before.

This article is educational and not tax advice. Confirm the figures for your own case with a chartered accountant.